Data centers and new power in Florida

23.0 GW of new power is waiting to connect to the grid in Florida — 232 requests across 48 counties. That is the 17th largest amount of any state. 185 projects are built, 472 withdrawn. Data as of 14 October 2026.

The power picture

What is happening with electricity in Florida

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Florida right now.

23.0 GW
of new power is waiting to connect
232 projects asked. Not yet approved. Roughly what 18.4 million homes use.
23.1 GW
has actually been built
185 projects switched on so far.
472
projects gave up
Withdrawn before being built. Normal nationally.

Where every request ever filed here ended up

  • Built 20%
  • Still waiting 26%
  • Withdrawn 52%
  • Paused 2%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Florida.

What kind of power is asking to connect

  • Solar 66%
  • Natural gas 15%
  • Nuclear 11%
  • Batteries 8%
  • Other 0%

By capacity requested. Data as of 14 October 2026.

All the numbers

908 requests ever filed
Waiting to connect
232
of 908 ever filed
Capacity requested
23.0 GW
asked for, not approved
Already built
23.1 GW
185 switched on
Built vs decided
28.2%
472 withdrawn
Counties involved
48
with five or more requests
Big new power users
none recorded
0 requests

Source: the interconnection queues of every transmission provider operating in Florida. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar20515.1 GW
Natural gas133.5 GW
Nuclear22.6 GW
Batteries101.8 GW
Other261 MW

Who runs the waiting list in Florida

Grid operator or utilityRequestsCapacity pending
FPL35715.1 GW
Duke3665.1 GW
OUC131.1 GW
JEA12995 MW
TEC105624 MW
SEC25138 MW
SOCO300 MW

Counties in Florida

48 with power on the waiting list

Every county with at least five requests on file. Open one to check an address, or see the schools near any mapped data center.

CountyWaitingCapacity queuedAlready built
Hendry County403.0 GW447 MW
Miami-Dade County32.7 GW248 MW
Osceola County92.0 GW584 MW
St. Lucie County241.8 GW670 MW
DeSoto County161.2 GW372 MW
Collier County151.1 GW74 MW
Charlotte County141.0 GW0 MW
Martin County141.0 GW224 MW
Duval County6995 MW84 MW
Pasco County4862 MW630 MW
Manatee County9683 MW856 MW
Indian River County8596 MW224 MW
Polk County8485 MW4.2 GW
Brevard County4448 MW298 MW
Bay County1400 MW224 MW
Pinellas County2397 MW1.3 GW
Highlands County4324 MW45 MW
Suwannee County4300 MW185 MW
Madison County4299 MW224 MW
Citrus County2299 MW2.0 GW
Hillsborough County4298 MW900 MW
Orange County5297 MW179 MW
Putnam County2274 MW298 MW
Leon County3249 MW0 MW
Jackson County2150 MW149 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.