Data centers and new power in Osceola County, FL

2.0 GW of new power is waiting to connect to the grid in Osceola County, FL — 9 active requests. Typical wait: 3.5 years. 3 projects are built, 19 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Osceola County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Osceola County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Osceola County right now.

2.0 GW
of new power is waiting to connect
9 projects asked. Not yet approved. Roughly what 1.6 million homes use.
584 MW
has actually been built
3 projects switched on so far.
3.5 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 10%
  • Still waiting 29%
  • Withdrawn 61%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Osceola County.

What kind of power is asking to connect

  • Natural gas 81%
  • Solar 19%

By capacity requested. Data as of 14 October 2026.

All the numbers

31 requests ever filed
Pending applications
9
of 31 ever filed
Capacity queued
2.0 GW
requested, not committed
Already built
584 MW
3 projects connected
Built vs decided
13.6%
19 withdrawn
Median wait
3.5 yr
for applications still pending
Connected capacity
2.7 GW
indicator, see note

Source: interconnection queues published by Duke, OUC. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built3584 MW9.7%
Still waiting92.0 GW29.0%
Withdrawn192.1 GW61.3%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Natural gas41.6 GW
Solar5373 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
142Solar617 MWwithdrawn2016-05Duke
Bull Creek (Osceola Generating Station)Natural gas555 MWactive2021-09OUC
4Natural gas537 MWactive1999-04Duke
15Natural gas368 MWwithdrawn2002-04Duke
72Natural gas340 MWcompleted2007-10Duke
FC100382Natural gas265 MWactive2025-12Duke
FC100386Natural gas265 MWactive2025-12Duke
74Natural gas170 MWcompleted2007-10Duke
325Solar75 MWactive2023-05Duke
326Solar75 MWactive2023-05Duke
165Solar74 MWwithdrawn2016-12Duke
191Solar74 MWwithdrawn2017-07Duke
193ASolar74 MWwithdrawn2017-08Duke
203ASolar74 MWwithdrawn2017-11Duke
203BSolar74 MWwithdrawn2017-11Duke

How Osceola County compares

#193 in the US · #3 in FL

Osceola County ranks #193 of 1,607 US counties by power waiting to connect, and #3 of 48 in Florida.

CountyWaitingCapacity queued
Hendry County403.0 GW
Miami-Dade County32.7 GW
St. Lucie County241.8 GW
DeSoto County161.2 GW
Collier County151.1 GW
Charlotte County141.0 GW
Martin County141.0 GW
Duval County6995 MW

Common questions about power in Osceola County

How long does it take to get power for a data center in Osceola County, FL?

The median wait for a project still in the interconnection queue in Osceola County is 3.5 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 3 projects in Osceola County have reached energization and 19 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Osceola County, FL?

2.0 GW is currently requested across 9 active interconnection requests, and 584 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Osceola County, FL a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Florida policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Osceola County — Duke, OUC — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Osceola County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.