Data centers and new power in Miami-Dade County, FL

2.7 GW of new power is waiting to connect to the grid in Miami-Dade County, FL — 3 active requests. Typical wait: 19.1 years. 4 projects are built, 1 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Miami-Dade County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Miami-Dade County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Miami-Dade County right now.

2.7 GW
of new power is waiting to connect
3 projects asked. Not yet approved. Roughly what 2.1 million homes use.
248 MW
has actually been built
4 projects switched on so far.
19.1 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 50%
  • Still waiting 38%
  • Withdrawn 12%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Miami-Dade County.

What kind of power is asking to connect

  • Nuclear 97%
  • Solar 3%

By capacity requested. Data as of 14 October 2026.

All the numbers

8 requests ever filed
Pending applications
3
of 8 ever filed
Capacity queued
2.7 GW
requested, not committed
Already built
248 MW
4 projects connected
Built vs decided
80.0%
1 withdrawn
Median wait
19.1 yr
for applications still pending
Connected capacity
3.3 GW
indicator, see note

Source: interconnection queues published by FPL. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built4248 MW50.0%
Still waiting32.7 GW37.5%
Withdrawn1300 MW12.5%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Nuclear22.6 GW
Solar174 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 9 by size
ProjectTypeCapacityStatusFiledQueue
107Nuclear1.3 GWactive2007-08FPL
108Nuclear1.3 GWactive2007-08FPL
629Batteries300 MWwithdrawn2024-01FPL
418Natural gas99 MWcompleted2020-09FPL
264Solar74 MWcompleted2017-06FPL
289Solar74 MWactive2017-06FPL
273Solar50 MWcompleted2017-06FPL
175Nuclear30 MWcompleted2016-01FPL
426Solar24 MWcompleted2022-02FPL

How Miami-Dade County compares

#131 in the US · #2 in FL

Miami-Dade County ranks #131 of 1,607 US counties by power waiting to connect, and #2 of 48 in Florida.

CountyWaitingCapacity queued
Hendry County403.0 GW
Osceola County92.0 GW
St. Lucie County241.8 GW
DeSoto County161.2 GW
Collier County151.1 GW
Charlotte County141.0 GW
Martin County141.0 GW
Duval County6995 MW

Common questions about power in Miami-Dade County

How long does it take to get power for a data center in Miami-Dade County, FL?

The median wait for a project still in the interconnection queue in Miami-Dade County is 19.1 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 4 projects in Miami-Dade County have reached energization and 1 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Miami-Dade County, FL?

2.7 GW is currently requested across 3 active interconnection requests, and 248 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Miami-Dade County, FL a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Florida policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Miami-Dade County — FPL — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Miami-Dade County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Miami-Dade County on the map County reports All of Florida