Data centers and new power in St. Lucie County, FL

1.8 GW of new power is waiting to connect to the grid in St. Lucie County, FL — 24 active requests. Typical wait: 4.5 years. 9 projects are built, 2 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside St. Lucie County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in St. Lucie County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in St. Lucie County right now.

1.8 GW
of new power is waiting to connect
24 projects asked. Not yet approved. Roughly what 1.4 million homes use.
670 MW
has actually been built
9 projects switched on so far.
4.5 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 26%
  • Still waiting 69%
  • Withdrawn 6%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for St. Lucie County.

What kind of power is asking to connect

  • Solar 100%

By capacity requested. Data as of 14 October 2026.

All the numbers

35 requests ever filed
Pending applications
24
of 35 ever filed
Capacity queued
1.8 GW
requested, not committed
Already built
670 MW
9 projects connected
Built vs decided
81.8%
2 withdrawn
Median wait
4.5 yr
for applications still pending
Connected capacity
3.5 GW
indicator, see note

Source: interconnection queues published by FPL. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built9670 MW25.7%
Still waiting241.8 GW68.6%
Withdrawn2149 MW5.7%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar241.8 GW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
275Solar74 MWcompleted2017-06FPL
292Solar74 MWcompleted2017-06FPL
298Solar74 MWwithdrawn2017-06FPL
334Solar74 MWcompleted2018-02FPL
347Solar74 MWactive2018-05FPL
352Solar74 MWcompleted2018-06FPL
369Solar74 MWcompleted2019-06FPL
399Solar74 MWcompleted2020-07FPL
401Solar74 MWcompleted2020-07FPL
402Solar74 MWcompleted2020-07FPL
403Solar74 MWcompleted2020-07FPL
404Solar74 MWactive2020-07FPL
406Solar74 MWactive2020-07FPL
407Solar74 MWactive2020-07FPL
408Solar74 MWactive2020-07FPL

How St. Lucie County compares

#218 in the US · #4 in FL

St. Lucie County ranks #218 of 1,607 US counties by power waiting to connect, and #4 of 48 in Florida.

CountyWaitingCapacity queued
Hendry County403.0 GW
Miami-Dade County32.7 GW
Osceola County92.0 GW
DeSoto County161.2 GW
Collier County151.1 GW
Charlotte County141.0 GW
Martin County141.0 GW
Duval County6995 MW

Common questions about power in St. Lucie County

How long does it take to get power for a data center in St. Lucie County, FL?

The median wait for a project still in the interconnection queue in St. Lucie County is 4.5 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 9 projects in St. Lucie County have reached energization and 2 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in St. Lucie County, FL?

1.8 GW is currently requested across 24 active interconnection requests, and 670 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is St. Lucie County, FL a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Florida policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving St. Lucie County — FPL — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.