Data centers and new power in Bay County, FL

400 MW of new power is waiting to connect to the grid in Bay County, FL — 1 active requests. Typical wait: 2.8 years. 4 projects are built, 4 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Bay County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Bay County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Bay County right now.

400 MW
of new power is waiting to connect
1 projects asked. Not yet approved. Roughly what 320,000 homes use.
224 MW
has actually been built
4 projects switched on so far.
2.8 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 44%
  • Still waiting 11%
  • Withdrawn 44%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Bay County.

What kind of power is asking to connect

  • Batteries 100%

By capacity requested. Data as of 14 October 2026.

All the numbers

9 requests ever filed
Pending applications
1
of 9 ever filed
Capacity queued
400 MW
requested, not committed
Already built
224 MW
4 projects connected
Built vs decided
50.0%
4 withdrawn
Median wait
2.8 yr
for applications still pending
Connected capacity
961 MW
indicator, see note

Source: interconnection queues published by FPL. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built4224 MW44.4%
Still waiting1400 MW11.1%
Withdrawn41.1 GW44.4%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Batteries1400 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 9 by size
ProjectTypeCapacityStatusFiledQueue
IC-758Natural gas741 MWwithdrawn2018-12SOCO
620Batteries400 MWactive2024-01FPL
621Batteries200 MWwithdrawn2024-01FPL
281Solar75 MWcompleted2020-04Duke
282Solar75 MWcompleted2020-04Duke
IC-710Solar65 MWwithdrawn2018-05SOCO
328BSolar50 MWcompleted2017-12FPL
IC-657Solar50 MWwithdrawn2017-12SOCO
419ASolar24 MWcompleted2021-01FPL

How Bay County compares

#696 in the US · #15 in FL

Bay County ranks #696 of 1,607 US counties by power waiting to connect, and #15 of 48 in Florida.

CountyWaitingCapacity queued
Hendry County403.0 GW
Miami-Dade County32.7 GW
Osceola County92.0 GW
St. Lucie County241.8 GW
DeSoto County161.2 GW
Collier County151.1 GW
Charlotte County141.0 GW
Martin County141.0 GW

Common questions about power in Bay County

How long does it take to get power for a data center in Bay County, FL?

The median wait for a project still in the interconnection queue in Bay County is 2.8 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 4 projects in Bay County have reached energization and 4 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Bay County, FL?

400 MW is currently requested across 1 active interconnection requests, and 224 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Bay County, FL a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Florida policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Bay County — FPL — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Bay County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Bay County on the map County reports All of Florida