Data centers and new power in Valencia Cty, NM

2.2 GW of new power is waiting to connect to the grid in Valencia Cty, NM — 11 active requests. Typical wait: 3.0 years. 9 projects are built, 30 withdrawn. Data as of 14 October 2026.

Live here?

How far is it from your house?

Meta Los Lunas, run by Meta, is in Valencia Cty and uses about as much electricity as 70,000 homes.

9 public schools are within 5 miles of it, 1 within one mile. Counted from the facility, not from any home. School list: US Department of Education.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Valencia Cty

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Valencia Cty right now.

2.2 GW
of new power is waiting to connect
11 projects asked. Not yet approved. Roughly what 1.8 million homes use.
282 MW
has actually been built
9 projects switched on so far.
3.0 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 18%
  • Still waiting 22%
  • Withdrawn 60%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Valencia Cty.

What kind of power is asking to connect

  • Batteries 61%
  • Solar 37%
  • Natural gas 2%

By capacity requested. Data as of 14 October 2026.

All the numbers

50 requests ever filed
Pending applications
11
of 50 ever filed
Capacity queued
2.2 GW
requested, not committed
Already built
282 MW
9 projects connected
Built vs decided
23.1%
30 withdrawn
Median wait
3.0 yr
for applications still pending
Connected capacity
621 MW
indicator, see note

Source: interconnection queues published by PNM. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built9282 MW18.0%
Still waiting112.2 GW22.0%
Withdrawn30964 MW60.0%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Batteries61.3 GW
Solar4820 MW
Natural gas142 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
IA-PNM-2023-11Batteries500 MWactive2023-01PNM
IA-PNM-2025-09Batteries400 MWactive2025-03PNM
IA-PNM-2025-01Solar371 MWactive2025-01PNM
WCoMlu3m0b0uWs Solar EnergyWind300 MWwithdrawn2010-04EPE
IA-PNM-2025-02Solar199 MWactive2025-01PNM
IA-PNM-2012-01Natural gas173 MWcompleted2012-07PNM
Huning EnergySolar150 MWactive2021-07PNM
IA-PNM-2023-18Batteries150 MWactive2023-09PNM
IA-PNM-2025-13Batteries150 MWactive2025-03PNM
IA-PNM-2018-07Solar150 MWwithdrawn2018-07PNM
IA-PNM-2020-21Solar100 MWactive2020-10PNM
IA-PNM-2023-13Solar100 MWwithdrawn2023-01PNM
IA-PNM-2025-11Batteries100 MWactive2025-03PNM
IA-PNM-2019-04Solar51 MWwithdrawn2019-04PNM
IA-PNM-2023-17Solar50 MWwithdrawn2023-09PNM

How Valencia Cty compares

#170 in the US · #3 in NM

Valencia Cty ranks #170 of 1,607 US counties by power waiting to connect, and #3 of 21 in New Mexico.

CountyWaitingCapacity queued
Bernalillo Cty213.9 GW
Roosevelt County92.4 GW
San Juan County92.1 GW
Santa Fe County91.6 GW
Torrence51.2 GW
Lea County91.1 GW
Doña Ana Cty7953 MW
Luna County8893 MW

Common questions about power in Valencia Cty

How long does it take to get power for a data center in Valencia Cty, NM?

The median wait for a project still in the interconnection queue in Valencia Cty is 3.0 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 9 projects in Valencia Cty have reached energization and 30 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Valencia Cty, NM?

2.2 GW is currently requested across 11 active interconnection requests, and 282 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Valencia Cty, NM a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our New Mexico policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Valencia Cty — PNM — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Valencia Cty

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Valencia Cty on the map County reports All of New Mexico