Data centers and new power in Bernalillo Cty, NM

3.9 GW of new power is waiting to connect to the grid in Bernalillo Cty, NM — 21 active requests. Typical wait: 4.5 years. 8 projects are built, 25 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Bernalillo Cty itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Bernalillo Cty

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Bernalillo Cty right now.

3.9 GW
of new power is waiting to connect
21 projects asked. Not yet approved. Roughly what 3.1 million homes use.
454 MW
has actually been built
8 projects switched on so far.
4.5 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 14%
  • Still waiting 37%
  • Withdrawn 44%
  • Paused 5%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Bernalillo Cty.

What kind of power is asking to connect

  • Solar 64%
  • Batteries 32%
  • Natural gas 4%

By capacity requested. Data as of 14 October 2026.

All the numbers

57 requests ever filed
Pending applications
21
of 57 ever filed
Capacity queued
3.9 GW
requested, not committed
Already built
454 MW
8 projects connected
Built vs decided
24.2%
25 withdrawn
Median wait
4.5 yr
for applications still pending
Connected capacity
1.2 GW
indicator, see note

Source: interconnection queues published by PNM. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built8454 MW14.0%
Still waiting213.9 GW36.8%
Withdrawn252.9 GW43.9%
Paused3—5.3%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar112.5 GW
Batteries91.3 GW
Natural gas1172 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
IA-PNM-2019-15Solar450 MWwithdrawn2019-04PNM
IA-PNM-2018-06Solar400 MWwithdrawn2018-07PNM
IA-PNM-2019-14Solar400 MWcompleted2019-04PNM
IA-PNM-2020-04Solar400 MWactive2020-01PNM
IA-PNM-2025-10Solar400 MWactive2025-03PNM
IA-PNM-2023-25Batteries350 MWwithdrawn2023-09PNM
Atrisco Solar IISolar300 MWsuspended2020-10PNM
IA-PNM-2021-10Solar300 MWactive2021-07PNM
IA-PNM-2025-06Solar250 MWactive2025-03PNM
IA-PNM-2021-22Solar220 MWwithdrawn2021-11PNM
Juan Tabo GridBatteries200 MWactive2021-06PNM
IA-PNM-2023-03Batteries200 MWactive2023-12PNM
IA-PNM-2023-04Solar200 MWactive2023-01PNM
IA-PNM-2023-05Solar200 MWactive2023-01PNM
IA-PNM-2019-17Solar200 MWwithdrawn2019-04PNM

How Bernalillo Cty compares

#77 in the US · #1 in NM

Bernalillo Cty ranks #77 of 1,607 US counties by power waiting to connect, and #1 of 21 in New Mexico.

CountyWaitingCapacity queued
Roosevelt County92.4 GW
Valencia Cty112.2 GW
San Juan County92.1 GW
Santa Fe County91.6 GW
Torrence51.2 GW
Lea County91.1 GW
Doña Ana Cty7953 MW
Luna County8893 MW

Common questions about power in Bernalillo Cty

How long does it take to get power for a data center in Bernalillo Cty, NM?

The median wait for a project still in the interconnection queue in Bernalillo Cty is 4.5 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 8 projects in Bernalillo Cty have reached energization and 25 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Bernalillo Cty, NM?

3.9 GW is currently requested across 21 active interconnection requests, and 454 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Bernalillo Cty, NM a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our New Mexico policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Bernalillo Cty — PNM — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Bernalillo Cty

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Bernalillo Cty on the map County reports All of New Mexico