Data centers and new power in Doña Ana Cty, NM
953 MW of new power is waiting to connect to the grid in Do√±a Ana Cty, NM — 7 active requests. Typical wait: 7.0 years. 0 projects are built, 6 withdrawn. Data as of 14 October 2026.
Is one near your house?
We have not mapped a large AI data center inside Do√±a Ana Cty itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.
What is happening with electricity in Doña Ana Cty
Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Doña Ana Cty right now.
Where every request ever filed here ended up
Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Do√±a Ana Cty.
What kind of power is asking to connect
By capacity requested. Data as of 14 October 2026.
All the numbers
15 requests ever filed
Source: interconnection queues published by EPE, PNM. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.
Outcome of every request filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 0 | 0 MW | 0.0% |
| Still waiting | 7 | 953 MW | 46.7% |
| Withdrawn | 6 | 363 MW | 40.0% |
| Paused | 2 | — | 13.3% |
Waiting to connect, by type of power
| Type | Projects | Capacity requested |
|---|---|---|
| Solar | 4 | 495 MW |
| Batteries | 1 | 400 MW |
| Geothermal | 2 | 58 MW |
Key dates for projects here
no dated windows published
| Queue | What closes | Closes | Standing |
|---|---|---|---|
| FERC | FERC large-load show cause — stakeholder comments on RTO responses Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70… | No date published yet | unconfirmed source |
| FERC | FERC RM26-4 — generic large-load rulemaking Still at ANOPR stage. | No date published yet | confirmed source |
| FERC | Georgia PSC - Georgia Power must file large-load contracts 30 days before execution A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed. | No date published yet | confirmed source |
A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.
The biggest projects on file
top 15 by size
| Project | Type | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| Va400B | Batteries | 400 MW | active | 2025-06 | EPE |
| Ve-DL-195SB | Solar | 195 MW | active | 2025-05 | EPE |
| D150S Project | Solar | 150 MW | suspended | 2017-09 | EPE |
| Ve-DL-150SB | Solar | 150 MW | active | 2025-06 | EPE |
| VE100S Project | Solar | 100 MW | active | 2019-09 | EPE |
| DS90S | Solar | 90 MW | withdrawn | 2014-10 | EPE |
| VS90SB | Solar | 90 MW | withdrawn | 2025-05 | EPE |
| VS75SB | Solar | 75 MW | suspended | 2022-09 | EPE |
| HJ73SB Project | Solar | 73 MW | withdrawn | 2021-09 | EPE |
| ST70S Project | Solar | 70 MW | withdrawn | 2017-09 | EPE |
| VE50S Project | Solar | 50 MW | active | 2019-09 | EPE |
| IA-PNM-2014-04 | Geothermal | 29 MW | active | 2014-03 | PNM |
| IA-PNM-2015-01 | Geothermal | 29 MW | active | 2015-07 | PNM |
| V20S | Solar | 20 MW | withdrawn | 2017-02 | EPE |
| AN20S Project | Solar | 20 MW | withdrawn | 2019-03 | EPE |
How Doña Ana Cty compares
#390 in the US · #8 in NM
Doña Ana Cty ranks #390 of 1,607 US counties by power waiting to connect, and #8 of 21 in New Mexico.
| County | Waiting | Capacity queued |
|---|---|---|
| Bernalillo Cty | 21 | 3.9 GW |
| Roosevelt County | 9 | 2.4 GW |
| Valencia Cty | 11 | 2.2 GW |
| San Juan County | 9 | 2.1 GW |
| Santa Fe County | 9 | 1.6 GW |
| Torrence | 5 | 1.2 GW |
| Lea County | 9 | 1.1 GW |
| Luna County | 8 | 893 MW |
Common questions about power in Doña Ana Cty
How long does it take to get power for a data center in Doña Ana Cty, NM?
The median wait for a project still in the interconnection queue in Doña Ana Cty is 7.0 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 0 projects in Doña Ana Cty have reached energization and 6 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.
How much capacity is available in Doña Ana Cty, NM?
953 MW is currently requested across 7 active interconnection requests, and 0 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.
Is Doña Ana Cty, NM a good site for a data center?
This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our New Mexico policy page.
Where does the data on this page come from?
The interconnection queue published by the transmission providers serving Do√±a Ana Cty — EPE, PNM — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.
Go deeper on Doña Ana Cty
The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.
Open Doña Ana Cty on the map County reports All of New Mexico