Data centers and new power in Torrence, NM

1.2 GW of new power is waiting to connect to the grid in Torrence, NM — 5 active requests. Typical wait: 7.5 years. 6 projects are built, 8 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Torrence itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Torrence

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Torrence right now.

1.2 GW
of new power is waiting to connect
5 projects asked. Not yet approved. Roughly what 946,000 homes use.
1.9 GW
has actually been built
6 projects switched on so far.
7.5 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 32%
  • Still waiting 26%
  • Withdrawn 42%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Torrence.

What kind of power is asking to connect

  • Wind 96%
  • Solar 4%

By capacity requested. Data as of 14 October 2026.

All the numbers

19 requests ever filed
Pending applications
5
of 19 ever filed
Capacity queued
1.2 GW
requested, not committed
Already built
1.9 GW
6 projects connected
Built vs decided
42.9%
8 withdrawn
Median wait
7.5 yr
for applications still pending
Connected capacity
2.2 GW
indicator, see note

Source: interconnection queues published by PNM. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built61.9 GW31.6%
Still waiting51.2 GW26.3%
Withdrawn81.9 GW42.1%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Wind41.1 GW
Solar150 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
IA-PNM-2007-10Wind700 MWcompleted2007-06PNM
IA-PNM-2019-06Wind700 MWwithdrawn2019-03PNM
IA-PNM-2018-04Wind674 MWcompleted2018-07PNM
IA-PNM-2016-02Wind402 MWactive2016-05PNM
IA-PNM-2025-19Wind400 MWactive2025-03PNM
IA-PNM-2025-16Wind306 MWwithdrawn2025-03PNM
Tecolote WindWind272 MWcompleted2019-04PNM
IA-PNM-2025-14Wind250 MWwithdrawn2025-03PNM
IA-PNM-2025-18Wind250 MWactive2025-03PNM
IA-PNM-2018-08Solar199 MWwithdrawn2018-07PNM
IA-PNM-2019-16Solar198 MWwithdrawn2019-04PNM
Duran MesaWind105 MWcompleted2020-08PNM
IA-PNM-2006-02Wind100 MWcompleted2006-08PNM
IA-PNM-2007-09Wind100 MWwithdrawn2007-05PNM
IA-PNM-2023-23Batteries100 MWwithdrawn2023-09PNM

How Torrence compares

#329 in the US · #6 in NM

Torrence ranks #329 of 1,607 US counties by power waiting to connect, and #6 of 21 in New Mexico.

CountyWaitingCapacity queued
Bernalillo Cty213.9 GW
Roosevelt County92.4 GW
Valencia Cty112.2 GW
San Juan County92.1 GW
Santa Fe County91.6 GW
Lea County91.1 GW
Doña Ana Cty7953 MW
Luna County8893 MW

Common questions about power in Torrence

How long does it take to get power for a data center in Torrence, NM?

The median wait for a project still in the interconnection queue in Torrence is 7.5 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 6 projects in Torrence have reached energization and 8 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Torrence, NM?

1.2 GW is currently requested across 5 active interconnection requests, and 1.9 GW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Torrence, NM a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our New Mexico policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Torrence — PNM — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.