Data centers and new power in Roosevelt County, NM

2.4 GW of new power is waiting to connect to the grid in Roosevelt County, NM — 9 active requests. Typical wait: 1.9 years. 3 projects are built, 28 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Roosevelt County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Roosevelt County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Roosevelt County right now.

2.4 GW
of new power is waiting to connect
9 projects asked. Not yet approved. Roughly what 2 million homes use.
522 MW
has actually been built
3 projects switched on so far.
1.9 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 8%
  • Still waiting 22%
  • Withdrawn 70%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Roosevelt County.

What kind of power is asking to connect

  • Solar + battery 41%
  • Solar 29%
  • Wind 27%
  • Batteries 4%

By capacity requested. Data as of 14 October 2026.

All the numbers

40 requests ever filed
Pending applications
9
of 40 ever filed
Capacity queued
2.4 GW
requested, not committed
Already built
522 MW
3 projects connected
Built vs decided
9.7%
28 withdrawn
Median wait
1.9 yr
for applications still pending
Connected capacity
942 MW
indicator, see note

Source: interconnection queues published by PNM, SPP. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built3522 MW7.5%
Still waiting92.4 GW22.5%
Withdrawn286.7 GW70.0%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar + battery21.0 GW
Solar4699 MW
Wind2650 MW
Batteries1100 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source
SPPSPP 2028 CPP Interconnection Cluster Study (ICS) application window
Definitive Interconnection System Impact Study cluster, post Order 2023 compliance.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
GEN-2008-093Wind525 MWwithdrawn2008-08SPP
GEN-2024-304Solar + battery500 MWactive2025-03SPP
GEN-2024-303Solar + battery500 MWactive2025-03SPP
GEN-2024-301Solar500 MWwithdrawn2025-03SPP
GEN-2024-302Solar500 MWwithdrawn2025-03SPP
GEN-2024-221Wind400 MWactive2025-03SPP
GEN-2024-222Wind400 MWwithdrawn2025-03SPP
GEN-2016-076Wind396 MWwithdrawn2016-06SPP
GEN-2024-159Solar300 MWactive2025-03SPP
IA-PNM-2017-05Wind300 MWwithdrawn2017-01PNM
GEN-2021-097Wind300 MWwithdrawn2021-05SPP
GEN-2008-069Wind298 MWwithdrawn2008-07SPP
GEN-2016-123Wind298 MWcompleted2016-11SPP
GEN-2015-010Wind251 MWwithdrawn2015-03SPP
GEN-2024-043Wind250 MWactive2024-10SPP

How Roosevelt County compares

#146 in the US · #2 in NM

Roosevelt County ranks #146 of 1,607 US counties by power waiting to connect, and #2 of 21 in New Mexico.

CountyWaitingCapacity queued
Bernalillo Cty213.9 GW
Valencia Cty112.2 GW
San Juan County92.1 GW
Santa Fe County91.6 GW
Torrence51.2 GW
Lea County91.1 GW
Doña Ana Cty7953 MW
Luna County8893 MW

Common questions about power in Roosevelt County

How long does it take to get power for a data center in Roosevelt County, NM?

The median wait for a project still in the interconnection queue in Roosevelt County is 1.9 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 3 projects in Roosevelt County have reached energization and 28 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Roosevelt County, NM?

2.4 GW is currently requested across 9 active interconnection requests, and 522 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Roosevelt County, NM a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our New Mexico policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Roosevelt County — PNM, SPP — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Roosevelt County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.