Data centers and new power in Massachusetts

9.7 GW of new power is waiting to connect to the grid in Massachusetts — 25 requests across 12 counties. That is the 40th largest amount of any state. 108 projects are built, 468 withdrawn. Data as of 14 October 2026.

The power picture

What is happening with electricity in Massachusetts

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Massachusetts right now.

9.7 GW
of new power is waiting to connect
25 projects asked. Not yet approved. Roughly what 7.8 million homes use.
9.2 GW
has actually been built
108 projects switched on so far.
468
projects gave up
Withdrawn before being built. Normal nationally.

Where every request ever filed here ended up

  • Built 18%
  • Still waiting 4%
  • Withdrawn 78%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Massachusetts.

What kind of power is asking to connect

  • Batteries 46%
  • Wind 42%
  • Nuclear 13%

By capacity requested. Data as of 14 October 2026.

All the numbers

601 requests ever filed
Waiting to connect
25
of 601 ever filed
Capacity requested
9.7 GW
asked for, not approved
Already built
9.2 GW
108 switched on
Built vs decided
18.8%
468 withdrawn
Counties involved
12
with five or more requests
Big new power users
none recorded
0 requests

Source: the interconnection queues of every transmission provider operating in Massachusetts. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Waiting to connect, by type of power

TypeProjectsCapacity requested
Batteries174.4 GW
Wind54.0 GW
Nuclear31.2 GW

Who runs the waiting list in Massachusetts

Grid operator or utilityRequestsCapacity pending
ISONE6019.7 GW

Counties in Massachusetts

12 with power on the waiting list

Every county with at least five requests on file. Open one to check an address, or see the schools near any mapped data center.

CountyWaitingCapacity queuedAlready built
Bristol County21.4 GW67 MW
Middlesex County41.2 GW404 MW
Suffolk County2550 MW58 MW
Barnstable County1500 MW338 MW
Norfolk County2470 MW2.2 GW
Berkshire County2426 MW939 MW
Essex County2425 MW798 MW
Worcester County2384 MW144 MW
Hampden County2295 MW284 MW
Plymouth County120 MW173 MW
Franklin County17 MW1.3 GW
Hampshire County00 MW15 MW

Key dates for projects here

1 dated · next closes 2026-11-19 (ISONE)
QueueWhat closesClosesStanding
ISONEISO-NE cluster request window
Cluster study under OATT Schedules 22, 23 and 25.
2026-11-19disputed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.