Data centers and new power in Essex County, MA

425 MW of new power is waiting to connect to the grid in Essex County, MA — 2 active requests. Typical wait: 2.4 years. 8 projects are built, 9 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Essex County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Essex County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Essex County right now.

425 MW
of new power is waiting to connect
2 projects asked. Not yet approved. Roughly what 340,000 homes use.
798 MW
has actually been built
8 projects switched on so far.
2.4 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 42%
  • Still waiting 11%
  • Withdrawn 47%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Essex County.

What kind of power is asking to connect

  • Batteries 100%

By capacity requested. Data as of 14 October 2026.

All the numbers

19 requests ever filed
Pending applications
2
of 19 ever filed
Capacity queued
425 MW
requested, not committed
Already built
798 MW
8 projects connected
Built vs decided
47.1%
9 withdrawn
Median wait
2.4 yr
for applications still pending
Connected capacity
1.2 GW
indicator, see note

Source: interconnection queues published by ISONE. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built8798 MW42.1%
Still waiting2425 MW10.5%
Withdrawn91.3 GW47.4%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Batteries2425 MW

Key dates for projects here

1 dated · next closes 2026-11-19 (ISONE)
QueueWhat closesClosesStanding
ISONEISO-NE cluster request window
Cluster study under OATT Schedules 22, 23 and 25.
2026-11-19disputed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
Footprint Combined Cycle UnitNatural gas716 MWcompleted2012-01ISONE
Simple CycleNatural gas478 MWwithdrawn2014-02ISONE
Battery StorageBatteries310 MWwithdrawn2022-04ISONE
Battery StorageBatteries241 MWwithdrawn2023-03ISONE
Battery StorageBatteries225 MWactive2024-06ISONE
Battery StorageBatteries200 MWactive2024-06ISONE
Battery StorageBatteries150 MWwithdrawn2019-03ISONE
Peabody PowerNatural gas97 MWwithdrawn2003-02ISONE
Simple Cycle Gas TurbineNatural gas62 MWcompleted2016-07ISONE
Gas Turbine IncreaseNatural gas11 MWcompleted2013-02ISONE
NG NEMA Group DER StudyBatteries10 MWwithdrawn2023-12ISONE
Salem Harbor Station IncreaseBatteries8 MWcompleted2010-12ISONE
NG NEMA Group DER StudySolar5 MWwithdrawn2023-12ISONE
BESSBatteries5 MWwithdrawn2025-01ISONE
Covanta Haverhill Landfill GasNatural gas2 MWcompleted2006-12ISONE

How Essex County compares

#679 in the US · #7 in MA

Essex County ranks #679 of 1,607 US counties by power waiting to connect, and #7 of 12 in Massachusetts.

CountyWaitingCapacity queued
Bristol County21.4 GW
Middlesex County41.2 GW
Suffolk County2550 MW
Barnstable County1500 MW
Norfolk County2470 MW
Berkshire County2426 MW
Worcester County2384 MW
Hampden County2295 MW

Common questions about power in Essex County

How long does it take to get power for a data center in Essex County, MA?

The median wait for a project still in the interconnection queue in Essex County is 2.4 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 8 projects in Essex County have reached energization and 9 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Essex County, MA?

425 MW is currently requested across 2 active interconnection requests, and 798 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Essex County, MA a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Massachusetts policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Essex County — ISONE — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.