Data centers and new power in Worcester County, MA
384 MW of new power is waiting to connect to the grid in Worcester County, MA — 2 active requests. Typical wait: 3.2 years. 17 projects are built, 84 withdrawn. Data as of 14 October 2026.
Is one near your house?
We have not mapped a large AI data center inside Worcester County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.
What is happening with electricity in Worcester County
Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Worcester County right now.
Where every request ever filed here ended up
Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Worcester County.
What kind of power is asking to connect
By capacity requested. Data as of 14 October 2026.
All the numbers
103 requests ever filed
Source: interconnection queues published by ISONE. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.
Outcome of every request filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 17 | 144 MW | 16.5% |
| Still waiting | 2 | 384 MW | 1.9% |
| Withdrawn | 84 | 6.1 GW | 81.6% |
| Paused | 0 | — | 0.0% |
Waiting to connect, by type of power
| Type | Projects | Capacity requested |
|---|---|---|
| Batteries | 2 | 384 MW |
Key dates for projects here
1 dated · next closes 2026-11-19 (ISONE)
| Queue | What closes | Closes | Standing |
|---|---|---|---|
| ISONE | ISO-NE cluster request window Cluster study under OATT Schedules 22, 23 and 25. | 2026-11-19 | disputed source |
| FERC | FERC large-load show cause — stakeholder comments on RTO responses Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70… | No date published yet | unconfirmed source |
| FERC | FERC RM26-4 — generic large-load rulemaking Still at ANOPR stage. | No date published yet | confirmed source |
| FERC | Georgia PSC - Georgia Power must file large-load contracts 30 days before execution A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed. | No date published yet | confirmed source |
A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.
The biggest projects on file
top 15 by size
| Project | Type | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| Combined Cycle | Natural gas | 1.0 GW | withdrawn | 2015-11 | ISONE |
| Combined Cycle CNR Only | Natural gas | 586 MW | withdrawn | 2015-02 | ISONE |
| Battery Storage | Batteries | 408 MW | withdrawn | 2024-04 | ISONE |
| Battery Storage | Batteries | 300 MW | withdrawn | 2024-04 | ISONE |
| Battery Storage | Batteries | 300 MW | withdrawn | 2023-04 | ISONE |
| Battery Storage | Batteries | 262 MW | withdrawn | 2023-06 | ISONE |
| Battery Storage | Batteries | 205 MW | withdrawn | 2024-06 | ISONE |
| Battery Storage | Batteries | 204 MW | active | 2022-10 | ISONE |
| Battery Storage | Batteries | 200 MW | withdrawn | 2023-04 | ISONE |
| Gas Turbine | Natural gas | 190 MW | withdrawn | 2006-10 | ISONE |
| Battery Storage | Batteries | 190 MW | withdrawn | 2023-12 | ISONE |
| Gas Turbine | Natural gas | 188 MW | withdrawn | 2008-12 | ISONE |
| Battery Storage | Batteries | 180 MW | active | 2024-05 | ISONE |
| Gas Turbine | Natural gas | 159 MW | withdrawn | 2007-05 | ISONE |
| Battery Storage | Batteries | 158 MW | withdrawn | 2022-08 | ISONE |
How Worcester County compares
#714 in the US · #8 in MA
Worcester County ranks #714 of 1,607 US counties by power waiting to connect, and #8 of 12 in Massachusetts.
| County | Waiting | Capacity queued |
|---|---|---|
| Bristol County | 2 | 1.4 GW |
| Middlesex County | 4 | 1.2 GW |
| Suffolk County | 2 | 550 MW |
| Barnstable County | 1 | 500 MW |
| Norfolk County | 2 | 470 MW |
| Berkshire County | 2 | 426 MW |
| Essex County | 2 | 425 MW |
| Hampden County | 2 | 295 MW |
Common questions about power in Worcester County
How long does it take to get power for a data center in Worcester County, MA?
The median wait for a project still in the interconnection queue in Worcester County is 3.2 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 17 projects in Worcester County have reached energization and 84 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.
How much capacity is available in Worcester County, MA?
384 MW is currently requested across 2 active interconnection requests, and 144 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.
Is Worcester County, MA a good site for a data center?
This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Massachusetts policy page.
Where does the data on this page come from?
The interconnection queue published by the transmission providers serving Worcester County — ISONE — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.
Go deeper on Worcester County
The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.