Data centers and new power in Colorado

50.3 GW of new power is waiting to connect to the grid in Colorado — 253 requests across 25 counties. That is the 6th largest amount of any state. 37 projects are built, 368 withdrawn. Data as of 14 October 2026.

The power picture

What is happening with electricity in Colorado

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Colorado right now.

50.3 GW
of new power is waiting to connect
253 projects asked. Not yet approved. Roughly what 40.3 million homes use.
3.2 GW
has actually been built
37 projects switched on so far.
368
projects gave up
Withdrawn before being built. Normal nationally.

Where every request ever filed here ended up

  • Built 5%
  • Still waiting 37%
  • Withdrawn 54%
  • Paused 3%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Colorado.

What kind of power is asking to connect

  • Solar 46%
  • Wind 29%
  • Solar + battery 9%
  • Natural gas 8%
  • Batteries 6%
  • Coal 2%

By capacity requested. Data as of 14 October 2026.

All the numbers

677 requests ever filed
Waiting to connect
253
of 677 ever filed
Capacity requested
50.3 GW
asked for, not approved
Already built
3.2 GW
37 switched on
Built vs decided
9.1%
368 withdrawn
Counties involved
25
with five or more requests
Big new power users
none recorded
0 requests

Source: the interconnection queues of every transmission provider operating in Colorado. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar12623.3 GW
Wind5814.7 GW
Solar + battery224.3 GW
Natural gas154.0 GW
Batteries273.2 GW
Coal2850 MW
Hydro352 MW

Who runs the waiting list in Colorado

Grid operator or utilityRequestsCapacity pending
PSCo39424.2 GW
SPP8312.1 GW
TSGT8710.0 GW
PRPA541.6 GW
CSU61.4 GW
BHCT511.0 GW
PacifiCorp20 MW

Counties in Colorado

25 with power on the waiting list

Every county with at least five requests on file. Open one to check an address, or see the schools near any mapped data center.

CountyWaitingCapacity queuedAlready built
Weld County377.1 GW290 MW
Kit Carson County336.5 GW506 MW
Pueblo County295.1 GW440 MW
Lincoln County184.6 GW0 MW
Morgan County123.0 GW0 MW
El Paso County143.0 GW513 MW
Cheyenne County82.6 GW0 MW
Adams County92.3 GW0 MW
Kiowa County52.1 GW0 MW
Yuma County71.9 GW0 MW
Logan County71.2 GW400 MW
Elbert County41.2 GW0 MW
Larimer County111.1 GW247 MW
Arapahoe County31.0 GW0 MW
Moffat County5944 MW0 MW
Prowers County4676 MW0 MW
Alamosa County11644 MW0 MW
Montezuma County4450 MW0 MW
Las Animas County2315 MW170 MW
Park County2254 MW0 MW
Baca County1238 MW0 MW
Boulder County3180 MW0 MW
Saguache County1170 MW0 MW
Huerfano County1150 MW148 MW
Mesa County14 MW0 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source
SPPSPP 2028 CPP Interconnection Cluster Study (ICS) application window
Definitive Interconnection System Impact Study cluster, post Order 2023 compliance.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.