Data centers and new power in Lincoln County, CO

4.6 GW of new power is waiting to connect to the grid in Lincoln County, CO — 18 active requests. Typical wait: 2.5 years. 0 projects are built, 14 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Lincoln County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Lincoln County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Lincoln County right now.

4.6 GW
of new power is waiting to connect
18 projects asked. Not yet approved. Roughly what 3.7 million homes use.
0 MW
has actually been built
0 projects switched on so far.
2.5 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Still waiting 55%
  • Withdrawn 42%
  • Paused 3%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Lincoln County.

What kind of power is asking to connect

  • Wind 73%
  • Solar 21%
  • Solar + battery 7%

By capacity requested. Data as of 14 October 2026.

All the numbers

33 requests ever filed
Pending applications
18
of 33 ever filed
Capacity queued
4.6 GW
requested, not committed
Already built
0 MW
0 projects connected
Built vs decided
0.0%
14 withdrawn
Median wait
2.5 yr
for applications still pending
Connected capacity
1.0 GW
indicator, see note

Source: interconnection queues published by CSU, PSCo, SPP, TSGT. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built00 MW0.0%
Still waiting184.6 GW54.5%
Withdrawn143.6 GW42.4%
Paused1—3.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Wind113.3 GW
Solar5948 MW
Solar + battery2300 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source
SPPSPP 2028 CPP Interconnection Cluster Study (ICS) application window
Definitive Interconnection System Impact Study cluster, post Order 2023 compliance.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
GI-2016-3Wind600 MWactive2016-02PSCo
GI-2016-6Wind600 MWwithdrawn2016-04PSCo
CSUT-2025-1Wind500 MWactive2025-03SPP
CSUT-2025-1Wind500 MWactive2025-03CSU
GI-2017-11Solar500 MWwithdrawn2017-03PSCo
GEN-2015-012Wind300 MWwithdrawn2015-03SPP
GEN-2014-015Wind300 MWwithdrawn2014-06SPP
GI-2016-4Wind300 MWactive2016-02PSCo
GI-TC-2024-20Solar250 MWactive2024-05SPP
GI-2007-13Wind250 MWactive2007-11PSCo
GI-2008-3Wind250 MWwithdrawn2008-04PSCo
GI-2017-50Solar250 MWwithdrawn2017-11PSCo
GI-2017-14Wind201 MWwithdrawn2017-05PSCo
GI-2017-23Wind201 MWwithdrawn2017-07PSCo
GI-2011-2Wind200 MWactive2011-03PSCo

How Lincoln County compares

#61 in the US · #4 in CO

Lincoln County ranks #61 of 1,607 US counties by power waiting to connect, and #4 of 25 in Colorado.

CountyWaitingCapacity queued
Weld County377.1 GW
Kit Carson County336.5 GW
Pueblo County295.1 GW
Morgan County123.0 GW
El Paso County143.0 GW
Cheyenne County82.6 GW
Adams County92.3 GW
Kiowa County52.1 GW

Common questions about power in Lincoln County

How long does it take to get power for a data center in Lincoln County, CO?

The median wait for a project still in the interconnection queue in Lincoln County is 2.5 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 0 projects in Lincoln County have reached energization and 14 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Lincoln County, CO?

4.6 GW is currently requested across 18 active interconnection requests, and 0 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Lincoln County, CO a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Colorado policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Lincoln County — CSU, PSCo, SPP, TSGT — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.