Data centers and new power in Pueblo County, CO

5.1 GW of new power is waiting to connect to the grid in Pueblo County, CO — 29 active requests. Typical wait: 3.4 years. 4 projects are built, 101 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Pueblo County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Pueblo County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Pueblo County right now.

5.1 GW
of new power is waiting to connect
29 projects asked. Not yet approved. Roughly what 4.1 million homes use.
440 MW
has actually been built
4 projects switched on so far.
3.4 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 3%
  • Still waiting 21%
  • Withdrawn 73%
  • Paused 4%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Pueblo County.

What kind of power is asking to connect

  • Solar 75%
  • Coal 17%
  • Batteries 9%

By capacity requested. Data as of 14 October 2026.

All the numbers

139 requests ever filed
Pending applications
29
of 139 ever filed
Capacity queued
5.1 GW
requested, not committed
Already built
440 MW
4 projects connected
Built vs decided
3.8%
101 withdrawn
Median wait
3.4 yr
for applications still pending
Connected capacity
3.6 GW
indicator, see note

Source: interconnection queues published by BHCT, PSCo, TSGT. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built4440 MW2.9%
Still waiting295.1 GW20.9%
Withdrawn10117.2 GW72.7%
Paused5—3.6%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar223.8 GW
Coal2850 MW
Batteries5435 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
GI-2020-07Solar1.0 GWwithdrawn2020-03PSCo
GI-2003-3Coal750 MWactive2003-11PSCo
GI-2017-37Solar575 MWwithdrawn2017-09PSCo
GI-2017-49Solar500 MWwithdrawn2017-11PSCo
GI-2021-19Wind500 MWwithdrawn2021-09PSCo
GI-2021-20Wind500 MWwithdrawn2021-09PSCo
GI-2017-35Solar400 MWwithdrawn2017-09PSCo
GI-2022-10Solar400 MWwithdrawn2022-04PSCo
GI-2024-05Solar400 MWactive2024-04PSCo
GI-2020-13Solar374 MWwithdrawn2020-09PSCo
GI-2017-29Wind350 MWwithdrawn2017-08PSCo
GI-2019-2Solar350 MWwithdrawn2019-02PSCo
GI-2022-14Solar330 MWwithdrawn2022-04PSCo
GI-CS-2025-21Solar325 MWactive2025-09TSGT
5RSC-2024-06Solar300 MWactive2024-01PSCo

How Pueblo County compares

#53 in the US · #3 in CO

Pueblo County ranks #53 of 1,607 US counties by power waiting to connect, and #3 of 25 in Colorado.

CountyWaitingCapacity queued
Weld County377.1 GW
Kit Carson County336.5 GW
Lincoln County184.6 GW
Morgan County123.0 GW
El Paso County143.0 GW
Cheyenne County82.6 GW
Adams County92.3 GW
Kiowa County52.1 GW

Common questions about power in Pueblo County

How long does it take to get power for a data center in Pueblo County, CO?

The median wait for a project still in the interconnection queue in Pueblo County is 3.4 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 4 projects in Pueblo County have reached energization and 101 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Pueblo County, CO?

5.1 GW is currently requested across 29 active interconnection requests, and 440 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Pueblo County, CO a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Colorado policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Pueblo County — BHCT, PSCo, TSGT — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.