Data centers and new power in Adams County, CO

2.3 GW of new power is waiting to connect to the grid in Adams County, CO — 9 active requests. Typical wait: 2.4 years. 0 projects are built, 16 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Adams County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Adams County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Adams County right now.

2.3 GW
of new power is waiting to connect
9 projects asked. Not yet approved. Roughly what 1.8 million homes use.
0 MW
has actually been built
0 projects switched on so far.
2.4 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Still waiting 35%
  • Withdrawn 62%
  • Paused 4%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Adams County.

What kind of power is asking to connect

  • Solar 45%
  • Wind 37%
  • Solar + battery 9%
  • Batteries 9%

By capacity requested. Data as of 14 October 2026.

All the numbers

26 requests ever filed
Pending applications
9
of 26 ever filed
Capacity queued
2.3 GW
requested, not committed
Already built
0 MW
0 projects connected
Built vs decided
0.0%
16 withdrawn
Median wait
2.4 yr
for applications still pending
Connected capacity
1.8 GW
indicator, see note

Source: interconnection queues published by PSCo, SPP, TSGT. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built00 MW0.0%
Still waiting92.3 GW34.6%
Withdrawn162.6 GW61.5%
Paused1—3.8%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar51.0 GW
Wind2846 MW
Solar + battery1199 MW
Batteries1199 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source
SPPSPP 2028 CPP Interconnection Cluster Study (ICS) application window
Definitive Interconnection System Impact Study cluster, post Order 2023 compliance.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
GI-2024-12Wind423 MWactive2024-05PSCo
GI-2024-13Wind423 MWactive2024-05PSCo
GI-2025-12Solar355 MWactive2025-05PSCo
GI-2023-4Solar310 MWwithdrawn2023-05PSCo
GI-2006-1cNatural gas264 MWwithdrawn2006-01PSCo
GI-2019-9Solar200 MWwithdrawn2019-09PSCo
GI-2020-16Solar200 MWwithdrawn2020-10PSCo
GI-2021-29Solar200 MWwithdrawn2021-10PSCo
GI-CS-2025-02Solar + battery199 MWactive2025-09SPP
5RSC-2024-24Solar199 MWactive2024-01PSCo
GI-2020-06Solar199 MWwithdrawn2020-03PSCo
GI-2021-14Solar199 MWwithdrawn2021-09PSCo
GI-2021-6Solar199 MWsuspended2021-04PSCo
GI-2024-09Batteries199 MWactive2024-05PSCo
GI-CS-2025-02Solar199 MWactive2025-09TSGT

How Adams County compares

#165 in the US · #8 in CO

Adams County ranks #165 of 1,607 US counties by power waiting to connect, and #8 of 25 in Colorado.

CountyWaitingCapacity queued
Weld County377.1 GW
Kit Carson County336.5 GW
Pueblo County295.1 GW
Lincoln County184.6 GW
Morgan County123.0 GW
El Paso County143.0 GW
Cheyenne County82.6 GW
Kiowa County52.1 GW

Common questions about power in Adams County

How long does it take to get power for a data center in Adams County, CO?

The median wait for a project still in the interconnection queue in Adams County is 2.4 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 0 projects in Adams County have reached energization and 16 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Adams County, CO?

2.3 GW is currently requested across 9 active interconnection requests, and 0 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Adams County, CO a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Colorado policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Adams County — PSCo, SPP, TSGT — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.