Data centers and new power in Deaf Smith County, TX

6.6 GW of new power is waiting to connect to the grid in Deaf Smith County, TX — 11 active requests. Typical wait: 3.3 years. 0 projects are built, 13 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Deaf Smith County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Deaf Smith County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Deaf Smith County right now.

6.6 GW
of new power is waiting to connect
11 projects asked. Not yet approved. Roughly what 5.3 million homes use.
0 MW
has actually been built
0 projects switched on so far.
3.3 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Still waiting 46%
  • Withdrawn 54%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Deaf Smith County.

What kind of power is asking to connect

  • Solar 48%
  • Wind 30%
  • Natural gas 19%
  • Batteries 3%

By capacity requested. Data as of 14 October 2026.

All the numbers

24 requests ever filed
Pending applications
11
of 24 ever filed
Capacity queued
6.6 GW
requested, not committed
Already built
0 MW
0 projects connected
Built vs decided
0.0%
13 withdrawn
Median wait
3.3 yr
for applications still pending
Connected capacity
710 MW
indicator, see note

Source: interconnection queues published by ERCOT. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built00 MW0.0%
Still waiting116.6 GW45.8%
Withdrawn132.6 GW54.2%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar63.2 GW
Wind31.9 GW
Natural gas11.3 GW
Batteries1207 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
ERCOTERCOT Batch 1 large load interconnection - applications not yet dated
Successor cycle to Batch Zero under PGRR145.
No date published yetconfirmed source
ERCOTERCOT generation interconnection — rolling
Not FERC-jurisdictional.
Open all year — no cut-offunconfirmed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source
ERCOTTexas SB 6 - large load curtailment protocol and equipment (PURA section 39.170(a))
All new large-load interconnections must carry ERCOT-controlled curtailment equipment.
Open all year — no cut-offconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
Aurelius 3 Natural GasNatural gas1.3 GWactive2029-01ERCOT
Aurelius SolarSolar1.1 GWactive2029-01ERCOT
Aurelius 3 WindWind705 MWactive2029-01ERCOT
Aurelius WindWind622 MWactive2029-01ERCOT
Aurelius 2 WindWind622 MWactive2029-01ERCOT
Renegade ProjectSolar516 MWactive2020-01ERCOT
Aurelius 2 SolarSolar445 MWactive2029-01ERCOT
Aurelius 3 SolarSolar445 MWactive2029-01ERCOT
Caliche Mound SolarSolar407 MWactive2023-01ERCOT
GEN-2014-067Natural gas356 MWwithdrawn2014-09SPP
Frio Flat WindWind305 MWwithdrawn2019-06ERCOT
GEN-2024-363Solar300 MWwithdrawn2025-03SPP
GEN-2017-029Wind270 MWwithdrawn2017-05SPP
GEN-2018-001Wind270 MWwithdrawn2018-02SPP
GEN-2015-101Wind240 MWwithdrawn2015-12SPP

How Deaf Smith County compares

#27 in the US · #12 in TX

Deaf Smith County ranks #27 of 1,607 US counties by power waiting to connect, and #12 of 183 in Texas.

CountyWaitingCapacity queued
Pecos County5521.2 GW
Brazoria County5511.7 GW
Milam County339.2 GW
Wharton County409.1 GW
Jack County188.6 GW
Hill County238.0 GW
Reeves County217.8 GW
Wilbarger County207.0 GW

Common questions about power in Deaf Smith County

How long does it take to get power for a data center in Deaf Smith County, TX?

The median wait for a project still in the interconnection queue in Deaf Smith County is 3.3 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 0 projects in Deaf Smith County have reached energization and 13 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Deaf Smith County, TX?

6.6 GW is currently requested across 11 active interconnection requests, and 0 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Deaf Smith County, TX a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Texas policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Deaf Smith County — ERCOT — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.