Data centers and new power in Reeves County, TX

7.8 GW of new power is waiting to connect to the grid in Reeves County, TX — 21 active requests. Typical wait: 0.8 years. 10 projects are built, 6 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Reeves County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Reeves County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Reeves County right now.

7.8 GW
of new power is waiting to connect
21 projects asked. Not yet approved. Roughly what 6.3 million homes use.
571 MW
has actually been built
10 projects switched on so far.
0.8 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 26%
  • Still waiting 55%
  • Withdrawn 16%
  • Paused 3%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Reeves County.

What kind of power is asking to connect

  • Natural gas 59%
  • Solar 14%
  • Wind 13%
  • Batteries 12%
  • Oil 2%

By capacity requested. Data as of 14 October 2026.

All the numbers

38 requests ever filed
Pending applications
21
of 38 ever filed
Capacity queued
7.8 GW
requested, not committed
Already built
571 MW
10 projects connected
Built vs decided
62.5%
6 withdrawn
Median wait
0.8 yr
for applications still pending
Connected capacity
621 MW
indicator, see note

Source: interconnection queues published by ERCOT. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built10571 MW26.3%
Still waiting217.8 GW55.3%
Withdrawn6492 MW15.8%
Paused1—2.6%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Natural gas94.6 GW
Solar41.1 GW
Wind21.0 GW
Batteries5951 MW
Oil1132 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
ERCOTERCOT Batch 1 large load interconnection - applications not yet dated
Successor cycle to Batch Zero under PGRR145.
No date published yetconfirmed source
ERCOTERCOT generation interconnection — rolling
Not FERC-jurisdictional.
Open all year — no cut-offunconfirmed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source
ERCOTTexas SB 6 - large load curtailment protocol and equipment (PURA section 39.170(a))
All new large-load interconnections must carry ERCOT-controlled curtailment equipment.
Open all year — no cut-offconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
Wolf Bone North Energy Center (OLD)Natural gas1.2 GWactive2029-01ERCOT
Kilby1 Part 6 Large Block Combined CycleNatural gas1.1 GWactive2029-01ERCOT
Kilby1 Part 4 Large Block Simple CycleNatural gas950 MWactive2028-01ERCOT
Glass Mountain Wind 2Wind519 MWactive2028-01ERCOT
Glass Mountain Wind 1Wind512 MWactive2029-01ERCOT
Trumpet SolarSolar455 MWactive2029-01ERCOT
Exergy Energy West Texas Natural Gas Reciprocating Power INatural gas400 MWactive2026-01ERCOT
Kilby1 Part 1 Small Block Simple CycleNatural gas371 MWactive2027-01ERCOT
Kilby1 Part 2 Tier1 BESSBatteries330 MWactive2028-01ERCOT
Cantaloupe SolarSolar307 MWactive2023-01ERCOT
Rodeo Ranch Energy StorageOther301 MWcompleted2021-09ERCOT
Cantaloupe StorageBatteries251 MWsuspended2020-12ERCOT
August Draw SolarSolar250 MWactive2025-01ERCOT
Bracero Pecan StorageBatteries238 MWactive2026-01ERCOT
Tolivar Power Plant (TEF- Due Diligence)Natural gas224 MWactive2027-01ERCOT

How Reeves County compares

#17 in the US · #7 in TX

Reeves County ranks #17 of 1,607 US counties by power waiting to connect, and #7 of 183 in Texas.

CountyWaitingCapacity queued
Pecos County5521.2 GW
Brazoria County5511.7 GW
Milam County339.2 GW
Wharton County409.1 GW
Jack County188.6 GW
Hill County238.0 GW
Wilbarger County207.0 GW
Mitchell County166.9 GW

Common questions about power in Reeves County

How long does it take to get power for a data center in Reeves County, TX?

The median wait for a project still in the interconnection queue in Reeves County is 0.8 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 10 projects in Reeves County have reached energization and 6 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Reeves County, TX?

7.8 GW is currently requested across 21 active interconnection requests, and 571 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Reeves County, TX a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Texas policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Reeves County — ERCOT — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Reeves County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.