Data centers and new power in Jack County, TX
8.6 GW of new power is waiting to connect to the grid in Jack County, TX — 18 active requests. Typical wait: 2.8 years. 0 projects are built, 1 withdrawn. Data as of 14 October 2026.
Is one near your house?
We have not mapped a large AI data center inside Jack County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.
What is happening with electricity in Jack County
Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Jack County right now.
Where every request ever filed here ended up
Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Jack County.
What kind of power is asking to connect
By capacity requested. Data as of 14 October 2026.
All the numbers
20 requests ever filed
Source: interconnection queues published by ERCOT. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.
Outcome of every request filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 0 | 0 MW | 0.0% |
| Still waiting | 18 | 8.6 GW | 90.0% |
| Withdrawn | 1 | 47 MW | 5.0% |
| Paused | 1 | — | 5.0% |
Waiting to connect, by type of power
| Type | Projects | Capacity requested |
|---|---|---|
| Natural gas | 3 | 3.2 GW |
| Batteries | 9 | 2.6 GW |
| Solar | 4 | 2.3 GW |
| Wind | 2 | 534 MW |
Key dates for projects here
no dated windows published
| Queue | What closes | Closes | Standing |
|---|---|---|---|
| ERCOT | ERCOT Batch 1 large load interconnection - applications not yet dated Successor cycle to Batch Zero under PGRR145. | No date published yet | confirmed source |
| ERCOT | ERCOT generation interconnection — rolling Not FERC-jurisdictional. | Open all year — no cut-off | unconfirmed source |
| FERC | FERC large-load show cause — stakeholder comments on RTO responses Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70… | No date published yet | unconfirmed source |
| FERC | FERC RM26-4 — generic large-load rulemaking Still at ANOPR stage. | No date published yet | confirmed source |
| FERC | Georgia PSC - Georgia Power must file large-load contracts 30 days before execution A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed. | No date published yet | confirmed source |
| ERCOT | Texas SB 6 - large load curtailment protocol and equipment (PURA section 39.170(a)) All new large-load interconnections must carry ERCOT-controlled curtailment equipment. | Open all year — no cut-off | confirmed source |
A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.
The biggest projects on file
top 15 by size
| Project | Type | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| Thunder Bird 2 Gas | Natural gas | 1.3 GW | active | 2028-01 | ERCOT |
| Thunder Bird 1 Gas | Natural gas | 1.3 GW | active | 2030-01 | ERCOT |
| Dovetail Solar 1 | Solar | 666 MW | active | 2024-01 | ERCOT |
| Dovetail Solar 2 | Solar | 666 MW | active | 2024-01 | ERCOT |
| Dovetail Solar 3 | Solar | 666 MW | active | 2024-01 | ERCOT |
| Jack County III – 345 kV | Natural gas | 660 MW | active | 2026-01 | ERCOT |
| Dovetail Storage | Batteries | 509 MW | active | 2024-01 | ERCOT |
| Pinnington Storage | Batteries | 503 MW | active | 2024-01 | ERCOT |
| O'Bannion Energy Storage | Batteries | 306 MW | active | 2025-01 | ERCOT |
| Wooderson Energy Storage | Batteries | 306 MW | active | 2025-01 | ERCOT |
| Fortuna Wind | Wind | 295 MW | active | 2022-01 | ERCOT |
| Possum Kingdom Solar | Solar | 262 MW | active | 2024-01 | ERCOT |
| Campsey Wind | Wind | 238 MW | active | 2023-01 | ERCOT |
| Liberty Senate Energy Storage 1 | Batteries | 207 MW | active | 2023-01 | ERCOT |
| Lightning Ridge Energy Storage | Batteries | 205 MW | active | 2026-01 | ERCOT |
How Jack County compares
#13 in the US · #5 in TX
Jack County ranks #13 of 1,607 US counties by power waiting to connect, and #5 of 183 in Texas.
| County | Waiting | Capacity queued |
|---|---|---|
| Pecos County | 55 | 21.2 GW |
| Brazoria County | 55 | 11.7 GW |
| Milam County | 33 | 9.2 GW |
| Wharton County | 40 | 9.1 GW |
| Hill County | 23 | 8.0 GW |
| Reeves County | 21 | 7.8 GW |
| Wilbarger County | 20 | 7.0 GW |
| Mitchell County | 16 | 6.9 GW |
Common questions about power in Jack County
How long does it take to get power for a data center in Jack County, TX?
The median wait for a project still in the interconnection queue in Jack County is 2.8 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 0 projects in Jack County have reached energization and 1 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.
How much capacity is available in Jack County, TX?
8.6 GW is currently requested across 18 active interconnection requests, and 0 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.
Is Jack County, TX a good site for a data center?
This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Texas policy page.
Where does the data on this page come from?
The interconnection queue published by the transmission providers serving Jack County — ERCOT — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.
Go deeper on Jack County
The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.