Data centers and new power in Middlesex County, NJ

0 MW of new power is waiting to connect to the grid in Middlesex County, NJ — 0 active requests. 27 projects are built, 83 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Middlesex County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Middlesex County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Middlesex County right now.

0 MW
of new power is waiting to connect
0 projects asked. Not yet approved.
6.7 GW
has actually been built
27 projects switched on so far.
83
projects gave up
Withdrawn before being built. Normal nationally.

Where every request ever filed here ended up

  • Built 25%
  • Withdrawn 75%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Middlesex County.

What kind of power is asking to connect

    By capacity requested. Data as of 14 October 2026.

    All the numbers

    110 requests ever filed
    Pending applications
    0
    of 110 ever filed
    Capacity queued
    0 MW
    requested, not committed
    Already built
    6.7 GW
    27 projects connected
    Built vs decided
    24.5%
    83 withdrawn

    Source: interconnection queues published by the transmission providers serving this county. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

    Outcome of every request filed here

    OutcomeProjectsCapacityShare
    Built276.7 GW24.5%
    Still waiting00 MW0.0%
    Withdrawn8336.8 GW75.5%
    Paused0—0.0%

    Waiting to connect, by type of power

    Key dates for projects here

    no dated windows published
    QueueWhat closesClosesStanding
    FERCFERC large-load show cause — stakeholder comments on RTO responses
    Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
    No date published yetunconfirmed source
    FERCFERC RM26-4 — generic large-load rulemaking
    Still at ANOPR stage.
    No date published yetconfirmed source
    FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
    A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
    No date published yetconfirmed source

    A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

    The biggest projects on file

    top 15 by size
    ProjectTypeCapacityStatusFiledQueue
    AH2-285Wind1.4 GWwithdrawn2022-03PJM
    AH2-286Wind1.4 GWwithdrawn2022-03PJM
    South AmboyNatural gas1.3 GWwithdrawn2008-07PJM
    Deans 500 kVWind1.3 GWwithdrawn2022-09PJM
    Werner 230 kVWind1.3 GWwithdrawn2022-09PJM
    Deans 500 kVWind1.3 GWwithdrawn2020-12PJM
    Werner 230 kV-Ravenwood 345 kVNot stated1.2 GWwithdrawn2021-02PJM
    Deans 500kVWind1.2 GWwithdrawn2018-06PJM
    Sewaren 230 kVWind1.2 GWwithdrawn2018-11PJM
    Branchburg-Deans 500kVNatural gas1.0 GWwithdrawn2008-05PJM
    Branchburg-Deans 500kVNatural gas1.0 GWwithdrawn2008-05PJM
    Red Oak 230kVNatural gas922 MWwithdrawn2009-09PJM
    Atlantic-South River 230kVNatural gas909 MWwithdrawn2015-05PJM
    Raritan River 230 kVNatural gas820 MWwithdrawn2017-09PJM
    SewarenNatural gas800 MWwithdrawn2001-03PJM

    How Middlesex County compares

    #1434 in the US · #18 in NJ

    Middlesex County ranks #1434 of 1,607 US counties by power waiting to connect, and #18 of 21 in New Jersey.

    CountyWaitingCapacity queued
    Salem County32.8 GW
    Bergen County22.0 GW
    Union County21.6 GW
    Hudson County2350 MW
    Atlantic County3308 MW
    Camden County1300 MW
    Warren County7181 MW
    Mercer County1170 MW

    Common questions about power in Middlesex County

    How long does it take to get power for a data center in Middlesex County, NJ?

    We do not yet have a median wait for Middlesex County. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 27 projects in Middlesex County have reached energization and 83 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

    How much capacity is available in Middlesex County, NJ?

    0 MW is currently requested across 0 active interconnection requests, and 6.7 GW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

    Is Middlesex County, NJ a good site for a data center?

    This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our New Jersey policy page.

    Where does the data on this page come from?

    The interconnection queue published by the transmission providers serving Middlesex County — the utilities in this area — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

    Go deeper on Middlesex County

    The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

    Open Middlesex County on the map County reports All of New Jersey