Data centers and new power in Hudson County, NJ

350 MW of new power is waiting to connect to the grid in Hudson County, NJ — 2 active requests. Typical wait: 6.8 years. 9 projects are built, 28 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Hudson County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Hudson County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Hudson County right now.

350 MW
of new power is waiting to connect
2 projects asked. Not yet approved. Roughly what 280,000 homes use.
1.9 GW
has actually been built
9 projects switched on so far.
6.8 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 23%
  • Still waiting 5%
  • Withdrawn 72%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Hudson County.

What kind of power is asking to connect

  • Batteries 100%

By capacity requested. Data as of 14 October 2026.

All the numbers

39 requests ever filed
Pending applications
2
of 39 ever filed
Capacity queued
350 MW
requested, not committed
Already built
1.9 GW
9 projects connected
Built vs decided
24.3%
28 withdrawn
Median wait
6.8 yr
for applications still pending
Connected capacity
1.3 GW
indicator, see note

Source: interconnection queues published by PJM. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built91.9 GW23.1%
Still waiting2350 MW5.1%
Withdrawn289.3 GW71.8%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Batteries2350 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
PJMDominion GS-5 (Virginia SCC PUR-2025-00058) - ESAs signed on or after this date carry the 14-year term
From this date the GS-5 large-load tariff carries a 14-year minimum term, alongside the reported 85% of contracted transmission demand minimum and $1…
No date published yetdisputed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
Bayonne 345kVNatural gas1.0 GWwithdrawn2016-03PJM
Hudson 230 kVNatural gas750 MWwithdrawn1998-08PJM
Kearny 230kVNatural gas750 MWwithdrawn2000-08PJM
Hudson 230kVNatural gas750 MWwithdrawn2002-09PJM
Hudson 230kVNatural gas705 MWwithdrawn2012-11PJM
Hudson 230kVCoal678 MWwithdrawn2010-12PJM
Hudson 230kVNatural gas660 MWwithdrawn2011-11PJM
HudsonNatural gas650 MWwithdrawn2000-12PJM
Liberty BESSBatteries600 MWwithdrawn2023-05NYISO
Hudson 230kVNatural gas550 MWwithdrawn2010-12PJM
KearnyNatural gas537 MWcompleted2013-02PJM
KearnyNatural gas497 MWcompleted2013-02PJM
Hudson - Essex 230kVNatural gas455 MWwithdrawn2006-07PJM
Kearny 138kVNatural gas300 MWwithdrawn2010-12PJM
Bergen 345 kVBatteries300 MWwithdrawn2020-03PJM

How Hudson County compares

#734 in the US · #4 in NJ

Hudson County ranks #734 of 1,607 US counties by power waiting to connect, and #4 of 21 in New Jersey.

CountyWaitingCapacity queued
Salem County32.8 GW
Bergen County22.0 GW
Union County21.6 GW
Atlantic County3308 MW
Camden County1300 MW
Warren County7181 MW
Mercer County1170 MW
Cumberland County3149 MW

Common questions about power in Hudson County

How long does it take to get power for a data center in Hudson County, NJ?

The median wait for a project still in the interconnection queue in Hudson County is 6.8 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 9 projects in Hudson County have reached energization and 28 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Hudson County, NJ?

350 MW is currently requested across 2 active interconnection requests, and 1.9 GW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Hudson County, NJ a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our New Jersey policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Hudson County — PJM — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Hudson County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Hudson County on the map County reports All of New Jersey