Data centers and new power in Cape May County, NJ

20 MW of new power is waiting to connect to the grid in Cape May County, NJ — 1 active requests. Typical wait: 6.9 years. 2 projects are built, 30 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Cape May County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Cape May County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Cape May County right now.

20 MW
of new power is waiting to connect
1 projects asked. Not yet approved. Roughly what 16,000 homes use.
4 MW
has actually been built
2 projects switched on so far.
6.9 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 6%
  • Still waiting 3%
  • Withdrawn 88%
  • Paused 3%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Cape May County.

What kind of power is asking to connect

  • Batteries 100%

By capacity requested. Data as of 14 October 2026.

All the numbers

34 requests ever filed
Pending applications
1
of 34 ever filed
Capacity queued
20 MW
requested, not committed
Already built
4 MW
2 projects connected
Built vs decided
6.2%
30 withdrawn
Median wait
6.9 yr
for applications still pending
Connected capacity
4 MW
indicator, see note

Source: interconnection queues published by PJM. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built24 MW5.9%
Still waiting120 MW2.9%
Withdrawn304.0 GW88.2%
Paused1—2.9%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Batteries120 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
PJMDominion GS-5 (Virginia SCC PUR-2025-00058) - ESAs signed on or after this date carry the 14-year term
From this date the GS-5 large-load tariff carries a 14-year minimum term, alongside the reported 85% of contracted transmission demand minimum and $1…
No date published yetdisputed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
BL England 138kVNatural gas565 MWwithdrawn2012-11PJM
BL England 138kVNatural gas486 MWwithdrawn2012-04PJM
BL England 138kVNatural gas452 MWwithdrawn2012-02PJM
BL England 138kVNatural gas452 MWwithdrawn2012-04PJM
BL England 138 kVWind432 MWsuspended2018-09PJM
BL England 138 kVWind432 MWwithdrawn2023-03PJM
England 138kVNatural gas350 MWwithdrawn2001-05PJM
Corson 138kVWind350 MWwithdrawn2007-10PJM
EnglandWind346 MWwithdrawn2008-01PJM
Middle 138kVNatural gas122 MWwithdrawn2005-09PJM
MiddleOil109 MWwithdrawn2007-09PJM
Middle 69kVOil97 MWwithdrawn2008-04PJM
Huron 69kVWind25 MWwithdrawn2011-01PJM
CorsonBatteries20 MWwithdrawn2008-01PJM
LewisWind20 MWwithdrawn2008-01PJM

How Cape May County compares

#1211 in the US · #14 in NJ

Cape May County ranks #1211 of 1,607 US counties by power waiting to connect, and #14 of 21 in New Jersey.

CountyWaitingCapacity queued
Salem County32.8 GW
Bergen County22.0 GW
Union County21.6 GW
Hudson County2350 MW
Atlantic County3308 MW
Camden County1300 MW
Warren County7181 MW
Mercer County1170 MW

Common questions about power in Cape May County

How long does it take to get power for a data center in Cape May County, NJ?

The median wait for a project still in the interconnection queue in Cape May County is 6.9 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 2 projects in Cape May County have reached energization and 30 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Cape May County, NJ?

20 MW is currently requested across 1 active interconnection requests, and 4 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Cape May County, NJ a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our New Jersey policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Cape May County — PJM — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.