Data centers and new power in Kentucky

15.2 GW of new power is waiting to connect to the grid in Kentucky — 87 requests across 37 counties. That is the 30th largest amount of any state. 24 projects are built, 365 withdrawn. Data as of 14 October 2026.

The power picture

What is happening with electricity in Kentucky

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Kentucky right now.

15.2 GW
of new power is waiting to connect
87 projects asked. Not yet approved. Roughly what 12.1 million homes use.
6.4 GW
has actually been built
24 projects switched on so far.
365
projects gave up
Withdrawn before being built. Normal nationally.

Where every request ever filed here ended up

  • Built 5%
  • Still waiting 18%
  • Withdrawn 76%
  • Paused 1%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Kentucky.

What kind of power is asking to connect

  • Natural gas 46%
  • Solar 44%
  • Batteries 9%
  • Wind 1%
  • Not stated 0%
  • Hydro 0%

By capacity requested. Data as of 14 October 2026.

All the numbers

482 requests ever filed
Waiting to connect
87
of 482 ever filed
Capacity requested
15.2 GW
asked for, not approved
Already built
6.4 GW
24 switched on
Built vs decided
6.2%
365 withdrawn
Counties involved
37
with five or more requests
Big new power users
none recorded
0 requests

Source: the interconnection queues of every transmission provider operating in Kentucky. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Waiting to connect, by type of power

TypeProjectsCapacity requested
Natural gas186.9 GW
Solar576.6 GW
Batteries71.3 GW
Wind1200 MW
Not stated175 MW
Hydro345 MW

Who runs the waiting list in Kentucky

Grid operator or utilityRequestsCapacity pending
LGE-KU1256.2 GW
TVA663.9 GW
PJM2283.8 GW
MISO631.3 GW

Counties in Kentucky

37 with power on the waiting list

Every county with at least five requests on file. Open one to check an address, or see the schools near any mapped data center.

CountyWaitingCapacity queuedAlready built
Jefferson County73.2 GW0 MW
Muhlenberg County61.4 GW1.3 GW
Trimble County9925 MW0 MW
Mercer County6922 MW0 MW
Henderson County3800 MW450 MW
Fleming County4548 MW0 MW
Mccraken3466 MW183 MW
Martin County2300 MW0 MW
Marion County3251 MW0 MW
Mason County1250 MW0 MW
Hopkins County2213 MW0 MW
Hardin County2202 MW0 MW
Marshall County1200 MW640 MW
Logan County1173 MW0 MW
Madison County2153 MW0 MW
Pike County2150 MW0 MW
Metcalfe County1106 MW90 MW
Lyon County2104 MW0 MW
Ballard County1100 MW0 MW
Breckinridge County1100 MW0 MW
Ohio County1100 MW0 MW
Boone County180 MW0 MW
Fayette County280 MW0 MW
Perry County180 MW0 MW
Webster County175 MW310 MW

Key dates for projects here

1 dated · next closes 2027-09-10 (MISO)
QueueWhat closesClosesStanding
MISOMISO DPP-2026 Definitive Planning Phase application deadline
Attachment X of the tariff and BPM-015.
2027-09-10confirmed source
PJMDominion GS-5 (Virginia SCC PUR-2025-00058) - ESAs signed on or after this date carry the 14-year term
From this date the GS-5 large-load tariff carries a 14-year minimum term, alongside the reported 85% of contracted transmission demand minimum and $1…
No date published yetdisputed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.