Data centers and new power in Mccraken, KY

466 MW of new power is waiting to connect to the grid in Mccraken, KY — 3 active requests. Typical wait: 2.6 years. 2 projects are built, 9 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Mccraken itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Mccraken

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Mccraken right now.

466 MW
of new power is waiting to connect
3 projects asked. Not yet approved. Roughly what 373,000 homes use.
183 MW
has actually been built
2 projects switched on so far.
2.6 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 13%
  • Still waiting 20%
  • Withdrawn 60%
  • Paused 7%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Mccraken.

What kind of power is asking to connect

  • Batteries 54%
  • Solar 46%

By capacity requested. Data as of 14 October 2026.

All the numbers

15 requests ever filed
Pending applications
3
of 15 ever filed
Capacity queued
466 MW
requested, not committed
Already built
183 MW
2 projects connected
Built vs decided
18.2%
9 withdrawn
Median wait
2.6 yr
for applications still pending
Connected capacity
1.7 GW
indicator, see note

Source: interconnection queues published by LGE-KU, TVA. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built2183 MW13.3%
Still waiting3466 MW20.0%
Withdrawn92.9 GW60.0%
Paused1—6.7%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Batteries1250 MW
Solar2216 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
137Other950 MWwithdrawn2000-11TVA
124Other640 MWwithdrawn2000-11TVA
125Other340 MWwithdrawn2000-11TVA
464Solar300 MWwithdrawn2020-12TVA
25RSC-005Batteries250 MWactive2025-07TVA
500Solar200 MWwithdrawn2022-05TVA
Bryan Road - McCracken County 161.0kVSolar150 MWwithdrawn2022-09MISO
LGE-GIS-2009-001Natural gas123 MWcompleted2009-02LGE-KU
222Natural gas122 MWwithdrawn2009-07TVA
226Natural gas122 MWwithdrawn2010-12TVA
LGE-GIS-2021-007Solar120 MWsuspended2021-03LGE-KU
LGE-GIS-2021-020Solar120 MWactive2021-06LGE-KU
609Solar96 MWactive2024-02TVA
Bryan Road - McCracken County 161.0kVSolar75 MWwithdrawn2022-09MISO
Shell - McCracken County 69.0kVSolar60 MWcompleted2021-03MISO

How Mccraken compares

#647 in the US · #7 in KY

Mccraken ranks #647 of 1,607 US counties by power waiting to connect, and #7 of 37 in Kentucky.

CountyWaitingCapacity queued
Jefferson County73.2 GW
Muhlenberg County61.4 GW
Trimble County9925 MW
Mercer County6922 MW
Henderson County3800 MW
Fleming County4548 MW
Martin County2300 MW
Marion County3251 MW

Common questions about power in Mccraken

How long does it take to get power for a data center in Mccraken, KY?

The median wait for a project still in the interconnection queue in Mccraken is 2.6 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 2 projects in Mccraken have reached energization and 9 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Mccraken, KY?

466 MW is currently requested across 3 active interconnection requests, and 183 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Mccraken, KY a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Kentucky policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Mccraken — LGE-KU, TVA — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.