Data centers and new power in Columbia County, WA
557 MW of new power is waiting to connect to the grid in Columbia County, WA — 4 active requests. Typical wait: 19.2 years. 2 projects are built, 12 withdrawn. Data as of 14 October 2026.
Is one near your house?
We have not mapped a large AI data center inside Columbia County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.
What is happening with electricity in Columbia County
Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Columbia County right now.
Where every request ever filed here ended up
Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Columbia County.
What kind of power is asking to connect
By capacity requested. Data as of 14 October 2026.
All the numbers
18 requests ever filed
Source: interconnection queues published by BPA. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.
Outcome of every request filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 2 | 234 MW | 11.1% |
| Still waiting | 4 | 557 MW | 22.2% |
| Withdrawn | 12 | 1.9 GW | 66.7% |
| Paused | 0 | — | 0.0% |
Waiting to connect, by type of power
| Type | Projects | Capacity requested |
|---|---|---|
| Wind | 3 | 407 MW |
| Solar | 1 | 150 MW |
Key dates for projects here
no dated windows published
| Queue | What closes | Closes | Standing |
|---|---|---|---|
| FERC | FERC large-load show cause — stakeholder comments on RTO responses Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70… | No date published yet | unconfirmed source |
| FERC | FERC RM26-4 — generic large-load rulemaking Still at ANOPR stage. | No date published yet | confirmed source |
| FERC | Georgia PSC - Georgia Power must file large-load contracts 30 days before execution A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed. | No date published yet | confirmed source |
A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.
The biggest projects on file
top 15 by size
| Project | Type | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| G0299 | Wind | 300 MW | withdrawn | 2007-11 | BPA |
| G0298 | Wind | 300 MW | withdrawn | 2007-11 | BPA |
| 300MW Lower Monumental-Starbuck | Wind | 300 MW | withdrawn | 2001-09 | BPA |
| Lower Snake Phase 1 | Wind | 250 MW | active | 2007-08 | BPA |
| G1070 | Solar | 220 MW | withdrawn | 2024-08 | BPA |
| 122 | Wind | 211 MW | completed | 2007-02 | PacifiCorp |
| G0847 | Solar | 150 MW | active | 2023-02 | BPA |
| Hopkins Ridge Wind | Wind | 150 MW | active | 2002-05 | BPA |
| 119 | Solar | 150 MW | withdrawn | 2021-08 | PSE |
| 137 | Solar | 150 MW | withdrawn | 2022-11 | PSE |
| 13 | Wind | 140 MW | withdrawn | 2001-09 | PacifiCorp |
| 115 | Wind | 140 MW | withdrawn | 2021-08 | PSE |
| XX | Solar | 92 MW | withdrawn | 2018-08 | PSE |
| 14 | Wind | 70 MW | withdrawn | 2001-09 | PacifiCorp |
| 115 | Wind | 40 MW | withdrawn | 2006-12 | PacifiCorp |
Big new power users asking to connect
10 on record
Requests to connect large new customers — data centers, factories, electrification — rather than power plants.
| Request | Capacity | Status | Queue | Stated use |
|---|---|---|---|---|
| CAC Green H2 Facility | 1.6 GW | withdrawn | BPA | not stated |
| PARS - Clatskanie | 680 MW | withdrawn | BPA | not stated |
| Starbuck 500 MW | 500 MW | active | BPA | not stated |
| PW1 & PW2 PARS | 250 MW | active | BPA | not stated |
| PARS - Betsy Johnson Substation (POD 4514) | 240 MW | active | BPA | not stated |
| Rainier PARS | 105 MW | active | BPA | not stated |
| Forge Ahead 105 MW | 100 MW | withdrawn | BPA | not stated |
| Armstrong Project | 99 MW | active | BPA | not stated |
| PARS - St. Helens Substation (POD 3043) | 70 MW | active | BPA | not stated |
| Dutch Canyon Substation | 50 MW | energized | BPA | not stated |
Most of these filings do not say what the power is for. “Not stated” is the filing's silence, not ours.
How Columbia County compares
#579 in the US · #15 in WA
Columbia County ranks #579 of 1,607 US counties by power waiting to connect, and #15 of 30 in Washington.
| County | Waiting | Capacity queued |
|---|---|---|
| Benton County | 20 | 10.9 GW |
| Yakima County | 14 | 6.5 GW |
| Klickitat County | 23 | 6.2 GW |
| Douglas County | 8 | 3.6 GW |
| Grant County | 12 | 3.5 GW |
| Lincoln County | 9 | 2.0 GW |
| Lewis County | 4 | 1.6 GW |
| Spokane County | 11 | 973 MW |
Common questions about power in Columbia County
How long does it take to get power for a data center in Columbia County, WA?
The median wait for a project still in the interconnection queue in Columbia County is 19.2 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 2 projects in Columbia County have reached energization and 12 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.
How much capacity is available in Columbia County, WA?
557 MW is currently requested across 4 active interconnection requests, and 234 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.
Is Columbia County, WA a good site for a data center?
This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Washington policy page.
Where does the data on this page come from?
The interconnection queue published by the transmission providers serving Columbia County — BPA — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.