Data centers and new power in Wayne County, NC

1.3 GW of new power is waiting to connect to the grid in Wayne County, NC — 23 active requests. Typical wait: 2.3 years. 0 projects are built, 13 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Wayne County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Wayne County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Wayne County right now.

1.3 GW
of new power is waiting to connect
23 projects asked. Not yet approved. Roughly what 1 million homes use.
0 MW
has actually been built
0 projects switched on so far.
2.3 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Still waiting 64%
  • Withdrawn 36%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Wayne County.

What kind of power is asking to connect

  • Batteries 64%
  • Solar 18%
  • Natural gas 13%
  • Other 5%

By capacity requested. Data as of 14 October 2026.

All the numbers

36 requests ever filed
Pending applications
23
of 36 ever filed
Capacity queued
1.3 GW
requested, not committed
Already built
0 MW
0 projects connected
Built vs decided
0.0%
13 withdrawn
Median wait
2.3 yr
for applications still pending
Connected capacity
2.2 GW
indicator, see note

Source: interconnection queues published by Duke. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built00 MW0.0%
Still waiting231.3 GW63.9%
Withdrawn13963 MW36.1%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Batteries4820 MW
Solar4229 MW
Natural gas14167 MW
Other167 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
897163Batteries260 MWactive2023-06Duke
PP00027Batteries260 MWactive2025-04Duke
565542Solar160 MWwithdrawn2022-06Duke
956161Batteries150 MWactive2024-06Duke
PP00028Batteries150 MWactive2025-04Duke
177922Solar145 MWwithdrawn2021-06Duke
563066Solar80 MWwithdrawn2022-06Duke
569890Solar80 MWactive2022-06Duke
896943Solar80 MWwithdrawn2023-06Duke
920609Solar80 MWwithdrawn2023-09Duke
961894Solar80 MWwithdrawn2024-09Duke
962543Solar80 MWwithdrawn2024-10Duke
977272Solar80 MWactive2025-06Duke
920661Solar72 MWwithdrawn2023-09Duke
963471Solar72 MWwithdrawn2024-09Duke

How Wayne County compares

#298 in the US · #6 in NC

Wayne County ranks #298 of 1,607 US counties by power waiting to connect, and #6 of 44 in North Carolina.

CountyWaitingCapacity queued
Pinal County4610.6 GW
Person County41.9 GW
Washington County61.6 GW
Anson County31.5 GW
Davidson County21.5 GW
Stokes County31.2 GW
Richmond County7974 MW
Robeson County9946 MW

Common questions about power in Wayne County

How long does it take to get power for a data center in Wayne County, NC?

The median wait for a project still in the interconnection queue in Wayne County is 2.3 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 0 projects in Wayne County have reached energization and 13 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Wayne County, NC?

1.3 GW is currently requested across 23 active interconnection requests, and 0 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Wayne County, NC a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our North Carolina policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Wayne County — Duke — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Wayne County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.