Data centers and new power in Robeson County, NC

946 MW of new power is waiting to connect to the grid in Robeson County, NC — 9 active requests. Typical wait: 1.3 years. 0 projects are built, 12 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Robeson County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Robeson County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Robeson County right now.

946 MW
of new power is waiting to connect
9 projects asked. Not yet approved. Roughly what 757,000 homes use.
0 MW
has actually been built
0 projects switched on so far.
1.3 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Still waiting 43%
  • Withdrawn 57%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Robeson County.

What kind of power is asking to connect

  • Other 49%
  • Batteries 42%
  • Solar 8%

By capacity requested. Data as of 14 October 2026.

All the numbers

21 requests ever filed
Pending applications
9
of 21 ever filed
Capacity queued
946 MW
requested, not committed
Already built
0 MW
0 projects connected
Built vs decided
0.0%
12 withdrawn
Median wait
1.3 yr
for applications still pending
Connected capacity
419 MW
indicator, see note

Source: interconnection queues published by Duke. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built00 MW0.0%
Still waiting9946 MW42.9%
Withdrawn12629 MW57.1%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Other3468 MW
Batteries3398 MW
Solar380 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
898999Batteries200 MWactive2023-06Duke
977328Other199 MWactive2025-06Duke
PP00047Other199 MWactive2025-08Duke
956244Batteries99 MWactive2024-06Duke
PP00026Batteries99 MWactive2025-04Duke
911073Solar80 MWwithdrawn2023-09Duke
962733Solar80 MWwithdrawn2024-09Duke
977265Solar80 MWwithdrawn2025-06Duke
138340Solar74 MWwithdrawn2020-12Duke
570150Solar70 MWwithdrawn2022-06Duke
897335Solar70 MWwithdrawn2023-06Duke
963472Solar70 MWactive2024-09Duke
PP00036Other70 MWactive2025-07Duke
17250Solar60 MWwithdrawn2017-08Duke
920653Solar55 MWwithdrawn2023-09Duke

How Robeson County compares

#395 in the US · #9 in NC

Robeson County ranks #395 of 1,607 US counties by power waiting to connect, and #9 of 44 in North Carolina.

CountyWaitingCapacity queued
Pinal County4610.6 GW
Person County41.9 GW
Washington County61.6 GW
Anson County31.5 GW
Davidson County21.5 GW
Wayne County231.3 GW
Stokes County31.2 GW
Richmond County7974 MW

Common questions about power in Robeson County

How long does it take to get power for a data center in Robeson County, NC?

The median wait for a project still in the interconnection queue in Robeson County is 1.3 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 0 projects in Robeson County have reached energization and 12 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Robeson County, NC?

946 MW is currently requested across 9 active interconnection requests, and 0 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Robeson County, NC a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our North Carolina policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Robeson County — Duke — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.