Data centers and new power in Pinal County, NC
10.6 GW of new power is waiting to connect to the grid in Pinal County, NC — 46 active requests. Typical wait: 3.7 years. 14 projects are built, 138 withdrawn. Data as of 14 October 2026.
Is one near your house?
We have not mapped a large AI data center inside Pinal County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.
What is happening with electricity in Pinal County
Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Pinal County right now.
Where every request ever filed here ended up
Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Pinal County.
What kind of power is asking to connect
By capacity requested. Data as of 14 October 2026.
All the numbers
198 requests ever filed
Source: interconnection queues published by APS, SRP, SRP_PV-PC, TEP, WAPA-DSW. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.
Outcome of every request filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 14 | 2.5 GW | 7.1% |
| Still waiting | 46 | 10.6 GW | 23.2% |
| Withdrawn | 138 | 32.0 GW | 69.7% |
| Paused | 0 | — | 0.0% |
Waiting to connect, by type of power
| Type | Projects | Capacity requested |
|---|---|---|
| Solar | 27 | 6.4 GW |
| Other | 11 | 2.3 GW |
| Batteries | 5 | 1.5 GW |
| Natural gas | 3 | 439 MW |
Key dates for projects here
no dated windows published
| Queue | What closes | Closes | Standing |
|---|---|---|---|
| FERC | FERC large-load show cause — stakeholder comments on RTO responses Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70… | No date published yet | unconfirmed source |
| FERC | FERC RM26-4 — generic large-load rulemaking Still at ANOPR stage. | No date published yet | confirmed source |
| FERC | Georgia PSC - Georgia Power must file large-load contracts 30 days before execution A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed. | No date published yet | confirmed source |
A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.
The biggest projects on file
top 15 by size
| Project | Type | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| Q469 | Solar | 1.6 GW | withdrawn | 2022-03 | APS |
| Q41 | Natural gas | 1.2 GW | withdrawn | 2017-07 | SRP |
| Q33 | Solar | 1.0 GW | withdrawn | 2023-10 | SRP_PV-PC |
| Q2507 | Solar | 990 MW | withdrawn | 2025-02 | SRP |
| Q260 | Natural gas | 900 MW | withdrawn | 2017-09 | APS |
| Q39 | Natural gas | 864 MW | withdrawn | 2017-04 | SRP |
| Q04 | Natural gas | 659 MW | withdrawn | 2008-09 | SRP_PV-PC |
| Q04 | Natural gas | 606 MW | withdrawn | 2008-08 | SRP |
| Q13 | Solar | 600 MW | completed | 2019-04 | SRP_PV-PC |
| PV-PC-Q13 | Solar | 600 MW | completed | 2019-04 | SRP_PV-PC |
| Q02 | Natural gas | 562 MW | completed | 2007-05 | SRP |
| SRP-Q02 | Natural gas | 562 MW | completed | 2007-05 | SRP |
| Q06 | Natural gas | 540 MW | withdrawn | 2008-08 | SRP |
| Q24 | Batteries | 533 MW | withdrawn | 2022-09 | SRP_PV-PC |
| Q2513 | Batteries | 529 MW | withdrawn | 2025-02 | SRP |
How Pinal County compares
#9 in the US · #1 in NC
Pinal County ranks #9 of 1,607 US counties by power waiting to connect, and #1 of 44 in North Carolina.
| County | Waiting | Capacity queued |
|---|---|---|
| Person County | 4 | 1.9 GW |
| Washington County | 6 | 1.6 GW |
| Anson County | 3 | 1.5 GW |
| Davidson County | 2 | 1.5 GW |
| Wayne County | 23 | 1.3 GW |
| Stokes County | 3 | 1.2 GW |
| Richmond County | 7 | 974 MW |
| Robeson County | 9 | 946 MW |
Common questions about power in Pinal County
How long does it take to get power for a data center in Pinal County, NC?
The median wait for a project still in the interconnection queue in Pinal County is 3.7 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 14 projects in Pinal County have reached energization and 138 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.
How much capacity is available in Pinal County, NC?
10.6 GW is currently requested across 46 active interconnection requests, and 2.5 GW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.
Is Pinal County, NC a good site for a data center?
This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our North Carolina policy page.
Where does the data on this page come from?
The interconnection queue published by the transmission providers serving Pinal County — APS, SRP, SRP_PV-PC, TEP, WAPA-DSW — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.
Go deeper on Pinal County
The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.