Data centers and new power in Wake County, NC

858 MW of new power is waiting to connect to the grid in Wake County, NC — 6 active requests. Typical wait: 3.2 years. 1 projects are built, 8 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Wake County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Wake County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Wake County right now.

858 MW
of new power is waiting to connect
6 projects asked. Not yet approved. Roughly what 686,000 homes use.
14 MW
has actually been built
1 projects switched on so far.
3.2 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 7%
  • Still waiting 40%
  • Withdrawn 53%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Wake County.

What kind of power is asking to connect

  • Other 70%
  • Batteries 18%
  • Solar 12%

By capacity requested. Data as of 14 October 2026.

All the numbers

15 requests ever filed
Pending applications
6
of 15 ever filed
Capacity queued
858 MW
requested, not committed
Already built
14 MW
1 projects connected
Built vs decided
11.1%
8 withdrawn
Median wait
3.2 yr
for applications still pending
Connected capacity
1.1 GW
indicator, see note

Source: interconnection queues published by Duke. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built114 MW6.7%
Still waiting6858 MW40.0%
Withdrawn84.4 GW53.3%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Other2600 MW
Batteries2156 MW
Solar2102 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
30612Natural gas1.4 GWwithdrawn2019-02Duke
17238Natural gas1.2 GWwithdrawn2017-08Duke
41400Nuclear1.1 GWwithdrawn2012-07Duke
977298Other300 MWactive2025-06Duke
PP00041Other300 MWactive2025-08Duke
899005Batteries200 MWwithdrawn2023-06Duke
568608Solar187 MWwithdrawn2022-06Duke
568598Solar152 MWwithdrawn2022-06Duke
38056Batteries100 MWactive2019-06Duke
919393Solar100 MWactive2023-09Duke
PP00032Other100 MWwithdrawn2025-06Duke
566170Batteries56 MWactive2022-06Duke
24751Nuclear14 MWcompleted2017-05Duke
897221Solar9 MWwithdrawn2023-06Duke
897777Solar2 MWactive2023-06Duke

How Wake County compares

#444 in the US · #10 in NC

Wake County ranks #444 of 1,607 US counties by power waiting to connect, and #10 of 44 in North Carolina.

CountyWaitingCapacity queued
Pinal County4610.6 GW
Person County41.9 GW
Washington County61.6 GW
Anson County31.5 GW
Davidson County21.5 GW
Wayne County231.3 GW
Stokes County31.2 GW
Richmond County7974 MW

Common questions about power in Wake County

How long does it take to get power for a data center in Wake County, NC?

The median wait for a project still in the interconnection queue in Wake County is 3.2 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 1 projects in Wake County have reached energization and 8 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Wake County, NC?

858 MW is currently requested across 6 active interconnection requests, and 14 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Wake County, NC a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our North Carolina policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Wake County — Duke — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Wake County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Wake County on the map County reports All of North Carolina