Data centers and new power in Scotland County, NC

165 MW of new power is waiting to connect to the grid in Scotland County, NC — 3 active requests. Typical wait: 3.0 years. 0 projects are built, 14 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Scotland County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Scotland County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Scotland County right now.

165 MW
of new power is waiting to connect
3 projects asked. Not yet approved. Roughly what 132,000 homes use.
0 MW
has actually been built
0 projects switched on so far.
3.0 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Still waiting 18%
  • Withdrawn 82%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Scotland County.

What kind of power is asking to connect

  • Solar 100%

By capacity requested. Data as of 14 October 2026.

All the numbers

17 requests ever filed
Pending applications
3
of 17 ever filed
Capacity queued
165 MW
requested, not committed
Already built
0 MW
0 projects connected
Built vs decided
0.0%
14 withdrawn
Median wait
3.0 yr
for applications still pending
Connected capacity
149 MW
indicator, see note

Source: interconnection queues published by Duke. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built00 MW0.0%
Still waiting3165 MW17.6%
Withdrawn141.0 GW82.4%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar3165 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
171542Solar80 MWwithdrawn2021-05Duke
568988Solar80 MWwithdrawn2022-06Duke
569632Solar80 MWactive2022-06Duke
570092Solar80 MWwithdrawn2022-06Duke
897025Solar80 MWwithdrawn2023-06Duke
897027Solar80 MWwithdrawn2023-06Duke
917441Solar80 MWwithdrawn2023-09Duke
917443Solar80 MWactive2023-09Duke
920637Solar80 MWwithdrawn2023-09Duke
962939Solar80 MWwithdrawn2024-10Duke
977271Solar80 MWwithdrawn2025-06Duke
5691Solar75 MWwithdrawn2016-06Duke
145458Solar74 MWwithdrawn2021-01Duke
177122Solar70 MWwithdrawn2021-08Duke
18250Solar60 MWwithdrawn2017-11Duke

How Scotland County compares

#984 in the US · #24 in NC

Scotland County ranks #984 of 1,607 US counties by power waiting to connect, and #24 of 44 in North Carolina.

CountyWaitingCapacity queued
Pinal County4610.6 GW
Person County41.9 GW
Washington County61.6 GW
Anson County31.5 GW
Davidson County21.5 GW
Wayne County231.3 GW
Stokes County31.2 GW
Richmond County7974 MW

Common questions about power in Scotland County

How long does it take to get power for a data center in Scotland County, NC?

The median wait for a project still in the interconnection queue in Scotland County is 3.0 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 0 projects in Scotland County have reached energization and 14 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Scotland County, NC?

165 MW is currently requested across 3 active interconnection requests, and 0 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Scotland County, NC a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our North Carolina policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Scotland County — Duke — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Scotland County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.