Data centers and new power in Beauregard Parish, LA

540 MW of new power is waiting to connect to the grid in Beauregard Parish, LA — 3 active requests. Typical wait: 1.0 years. 1 projects are built, 24 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Beauregard Parish itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Beauregard Parish

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Beauregard Parish right now.

540 MW
of new power is waiting to connect
3 projects asked. Not yet approved. Roughly what 432,000 homes use.
200 MW
has actually been built
1 projects switched on so far.
1.0 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 4%
  • Still waiting 11%
  • Withdrawn 86%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Beauregard Parish.

What kind of power is asking to connect

  • Solar 100%

By capacity requested. Data as of 14 October 2026.

All the numbers

28 requests ever filed
Pending applications
3
of 28 ever filed
Capacity queued
540 MW
requested, not committed
Already built
200 MW
1 projects connected
Built vs decided
4.0%
24 withdrawn
Median wait
1.0 yr
for applications still pending
Connected capacity
62 MW
indicator, see note

Source: interconnection queues published by MISO. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built1200 MW3.6%
Still waiting3540 MW10.7%
Withdrawn245.4 GW85.7%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar3540 MW

Key dates for projects here

1 dated · next closes 2027-09-10 (MISO)
QueueWhat closesClosesStanding
MISOMISO DPP-2026 Definitive Planning Phase application deadline
Attachment X of the tariff and BPM-015.
2027-09-10confirmed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
Penton 230KV SubstationSolar + battery810 MWwithdrawn2022-09MISO
Cooper-Penton Road 230kVSolar + battery410 MWwithdrawn2022-09MISO
COLE to PENTON 230.0 kVSolar386 MWwithdrawn2025-04MISO
RhodesSolar300 MWwithdrawn2021-09MISO
Cooper to Penton Road 230kVSolar + battery276 MWwithdrawn2022-09MISO
CLECO Cooper-Penton Road 230kV LineSolar + battery260 MWwithdrawn2021-08MISO
Cole - Penton Road 230.0kVSolar250 MWwithdrawn2024-04MISO
Bon Wier to Cooper 138 kVSolar250 MWwithdrawn2022-09MISO
West Bay - Centennial 138 kVSolar250 MWwithdrawn2022-09MISO
ColeSolar + battery250 MWwithdrawn2025-09MISO
Cooper - Penton Road 230kV LineSolar200 MWwithdrawn2019-04MISO
Cooper - Penton Road 230kV LineSolar200 MWcompleted2019-04MISO
Cooper - Penton 230 kV LineSolar200 MWwithdrawn2019-04MISO
Cooper to Penton Road 230 kVSolar200 MWwithdrawn2022-09MISO
Roy S Nelson - DeRidder Mill 138 kVSolar200 MWwithdrawn2022-09MISO

How Beauregard Parish compares

#595 in the US · #12 in LA

Beauregard Parish ranks #595 of 1,607 US counties by power waiting to connect, and #12 of 31 in Louisiana.

Common questions about power in Beauregard Parish

How long does it take to get power for a data center in Beauregard Parish, LA?

The median wait for a project still in the interconnection queue in Beauregard Parish is 1.0 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 1 projects in Beauregard Parish have reached energization and 24 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Beauregard Parish, LA?

540 MW is currently requested across 3 active interconnection requests, and 200 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Beauregard Parish, LA a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Louisiana policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Beauregard Parish — MISO — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Beauregard Parish

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Beauregard Parish on the map County reports All of Louisiana