Data centers and new power in Ouachita Parish, LA

1.2 GW of new power is waiting to connect to the grid in Ouachita Parish, LA — 4 active requests. Typical wait: 4.1 years. 3 projects are built, 7 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Ouachita Parish itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Ouachita Parish

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Ouachita Parish right now.

1.2 GW
of new power is waiting to connect
4 projects asked. Not yet approved. Roughly what 944,000 homes use.
350 MW
has actually been built
3 projects switched on so far.
4.1 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 21%
  • Still waiting 29%
  • Withdrawn 50%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Ouachita Parish.

What kind of power is asking to connect

  • Solar 100%

By capacity requested. Data as of 14 October 2026.

All the numbers

14 requests ever filed
Pending applications
4
of 14 ever filed
Capacity queued
1.2 GW
requested, not committed
Already built
350 MW
3 projects connected
Built vs decided
30.0%
7 withdrawn
Median wait
4.1 yr
for applications still pending
Connected capacity
2.0 GW
indicator, see note

Source: interconnection queues published by MISO. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built3350 MW21.4%
Still waiting41.2 GW28.6%
Withdrawn72.1 GW50.0%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar41.2 GW

Key dates for projects here

1 dated · next closes 2027-09-10 (MISO)
QueueWhat closesClosesStanding
MISOMISO DPP-2026 Definitive Planning Phase application deadline
Attachment X of the tariff and BPM-015.
2027-09-10confirmed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 14 by size
ProjectTypeCapacityStatusFiledQueue
STERLINGTON 500 SWYDNatural gas1.5 GWwithdrawn2025-05MISO
CargasSolar500 MWactive2022-09MISO
CargasSolar500 MWactive2022-09MISO
BASTROP (CAHOON) - STERLINGTON 115 SWYD 115.0kVSolar225 MWcompleted2021-12MISO
Rilla - Riverton 115kV Line TapSolar100 MWwithdrawn2017-06MISO
Rilla 115 kV SubstationSolar100 MWcompleted2019-04MISO
Rilla 115kVSolar100 MWwithdrawn2021-07MISO
RILLA - RIVERTON 115.0kVSolar100 MWactive2022-09MISO
CottonSolar100 MWwithdrawn2025-09MISO
RILLA - RIVERTON 115.0kVSolar93 MWwithdrawn2025-10MISO
PRAIRIE ROADSolar80 MWactive2022-09MISO
Selman Field 69 kV SubstationSolar80 MWwithdrawn2022-09MISO
RILLASolar75 MWwithdrawn2025-08MISO
Rilla 115kV substation (Same as J1239)Solar25 MWcompleted2021-11MISO

How Ouachita Parish compares

#330 in the US · #4 in LA

Ouachita Parish ranks #330 of 1,607 US counties by power waiting to connect, and #4 of 31 in Louisiana.

Common questions about power in Ouachita Parish

How long does it take to get power for a data center in Ouachita Parish, LA?

The median wait for a project still in the interconnection queue in Ouachita Parish is 4.1 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 3 projects in Ouachita Parish have reached energization and 7 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Ouachita Parish, LA?

1.2 GW is currently requested across 4 active interconnection requests, and 350 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Ouachita Parish, LA a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Louisiana policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Ouachita Parish — MISO — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Ouachita Parish

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Ouachita Parish on the map County reports All of Louisiana