Data centers and new power in Acadia Parish, LA

120 MW of new power is waiting to connect to the grid in Acadia Parish, LA — 1 active requests. Typical wait: 4.1 years. 5 projects are built, 8 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Acadia Parish itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Acadia Parish

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Acadia Parish right now.

120 MW
of new power is waiting to connect
1 projects asked. Not yet approved. Roughly what 96,000 homes use.
569 MW
has actually been built
5 projects switched on so far.
4.1 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 36%
  • Still waiting 7%
  • Withdrawn 57%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Acadia Parish.

What kind of power is asking to connect

  • Solar 100%

By capacity requested. Data as of 14 October 2026.

All the numbers

14 requests ever filed
Pending applications
1
of 14 ever filed
Capacity queued
120 MW
requested, not committed
Already built
569 MW
5 projects connected
Built vs decided
38.5%
8 withdrawn
Median wait
4.1 yr
for applications still pending
Connected capacity
1.8 GW
indicator, see note

Source: interconnection queues published by MISO. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built5569 MW35.7%
Still waiting1120 MW7.1%
Withdrawn81.2 GW57.1%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar1120 MW

Key dates for projects here

1 dated · next closes 2027-09-10 (MISO)
QueueWhat closesClosesStanding
MISOMISO DPP-2026 Definitive Planning Phase application deadline
Attachment X of the tariff and BPM-015.
2027-09-10confirmed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 14 by size
ProjectTypeCapacityStatusFiledQueue
RICHARD - WELLS 500.0kVSolar550 MWwithdrawn2024-04MISO
Acadia - Scanlan 138kV LineSolar150 MWwithdrawn2019-04MISO
RICHARD - SCOTT 138.0kVSolar150 MWcompleted2020-06MISO
Bayou CoveSolar144 MWcompleted2021-12MISO
Habetz - Sellers Road 138 kV LineSolar120 MWwithdrawn2022-09MISO
ACADIA - COLONIAL ACADEMY CO 138.0kVSolar120 MWactive2022-09MISO
Bayou Cove - Richard 138 kV circuit 2Solar110 MWwithdrawn2022-09MISO
Richard 138 kVSolar100 MWcompleted2021-08MISO
Bayou Cove to Richard 138kV (Circuit 258)Solar100 MWcompleted2020-06MISO
Scanlan (Cajun) to Bosco SS 138 kV lineSolar + battery100 MWwithdrawn2022-09MISO
Richard 138kVSolar75 MWwithdrawn2022-09MISO
Richard 138kVSolar75 MWcompleted2021-10MISO
Richard (Bus #335366) to Colonial Academy (Bus #335375) 138kVSolar + battery75 MWwithdrawn2022-09MISO
Bayou Cove - Richard 138 kV Line TapSolar50 MWwithdrawn2018-03MISO

How Acadia Parish compares

#1058 in the US · #23 in LA

Acadia Parish ranks #1058 of 1,607 US counties by power waiting to connect, and #23 of 31 in Louisiana.

Common questions about power in Acadia Parish

How long does it take to get power for a data center in Acadia Parish, LA?

The median wait for a project still in the interconnection queue in Acadia Parish is 4.1 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 5 projects in Acadia Parish have reached energization and 8 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Acadia Parish, LA?

120 MW is currently requested across 1 active interconnection requests, and 569 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Acadia Parish, LA a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Louisiana policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Acadia Parish — MISO — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Acadia Parish

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Acadia Parish on the map County reports All of Louisiana