Data centers and new power in Isle of Wight County, VA

637 MW of new power is waiting to connect to the grid in Isle of Wight County, VA — 6 active requests. Typical wait: 8.1 years. 2 projects are built, 14 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Isle of Wight County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Isle of Wight County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Isle of Wight County right now.

637 MW
of new power is waiting to connect
6 projects asked. Not yet approved. Roughly what 510,000 homes use.
260 MW
has actually been built
2 projects switched on so far.
8.1 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 9%
  • Still waiting 26%
  • Withdrawn 61%
  • Paused 4%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Isle of Wight County.

What kind of power is asking to connect

  • Solar 100%

By capacity requested. Data as of 14 October 2026.

All the numbers

23 requests ever filed
Pending applications
6
of 23 ever filed
Capacity queued
637 MW
requested, not committed
Already built
260 MW
2 projects connected
Built vs decided
12.5%
14 withdrawn
Median wait
8.1 yr
for applications still pending
Connected capacity
337 MW
indicator, see note

Source: interconnection queues published by PJM. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built2260 MW8.7%
Still waiting6637 MW26.1%
Withdrawn141.4 GW60.9%
Paused1—4.3%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar6637 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
PJMDominion GS-5 (Virginia SCC PUR-2025-00058) - ESAs signed on or after this date carry the 14-year term
From this date the GS-5 large-load tariff carries a 14-year minimum term, alongside the reported 85% of contracted transmission demand minimum and $1…
No date published yetdisputed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
Surry - Yadkin 500 kVSolar450 MWwithdrawn2021-09PJM
Smithfield 230 kVBatteries250 MWwithdrawn2021-03PJM
Septa 500kVSolar240 MWcompleted2016-11PJM
Septa 500kVSolar240 MWactive2017-03PJM
Smithfield-Surry 230kVSolar160 MWwithdrawn2016-02PJM
Poolesville - Winchester 230 kVSolar104 MWwithdrawn2021-09PJM
Suffolk-Poe 115 kVSolar100 MWwithdrawn2018-03PJM
Smithfield-Surry 230 kVSolar99 MWactive2021-09PJM
Myrtle-Windsor 115 kVSolar91 MWactive2019-04PJM
Myrtle-Windsor 115 kVSolar91 MWwithdrawn2023-02PJM
Ivor-Oak Ridge 115kVSolar85 MWactive2017-03PJM
Myrtle-Windsor 115 kVSolar71 MWactive2019-03PJM
Surry-Chuckatuck 230 kVSolar70 MWwithdrawn2021-02PJM
Poolesville-Winchester 230 kVSolar54 MWwithdrawn2020-09PJM
Myrtle-Windsor DP 115kVSolar51 MWactive2018-03PJM

How Isle of Wight County compares

#540 in the US · #17 in VA

Isle of Wight County ranks #540 of 1,607 US counties by power waiting to connect, and #17 of 71 in Virginia.

Common questions about power in Isle of Wight County

How long does it take to get power for a data center in Isle of Wight County, VA?

The median wait for a project still in the interconnection queue in Isle of Wight County is 8.1 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 2 projects in Isle of Wight County have reached energization and 14 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Isle of Wight County, VA?

637 MW is currently requested across 6 active interconnection requests, and 260 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Isle of Wight County, VA a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Virginia policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Isle of Wight County — PJM — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Isle of Wight County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Isle of Wight County on the map County reports All of Virginia