Data centers and new power in Halifax County, VA

892 MW of new power is waiting to connect to the grid in Halifax County, VA — 6 active requests. Typical wait: 5.8 years. 15 projects are built, 32 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Halifax County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Halifax County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Halifax County right now.

892 MW
of new power is waiting to connect
6 projects asked. Not yet approved. Roughly what 714,000 homes use.
1.3 GW
has actually been built
15 projects switched on so far.
5.8 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 28%
  • Still waiting 11%
  • Withdrawn 60%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Halifax County.

What kind of power is asking to connect

  • Solar 83%
  • Batteries 17%

By capacity requested. Data as of 14 October 2026.

All the numbers

53 requests ever filed
Pending applications
6
of 53 ever filed
Capacity queued
892 MW
requested, not committed
Already built
1.3 GW
15 projects connected
Built vs decided
31.9%
32 withdrawn
Median wait
5.8 yr
for applications still pending
Connected capacity
1.4 GW
indicator, see note

Source: interconnection queues published by PJM. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built151.3 GW28.3%
Still waiting6892 MW11.3%
Withdrawn323.1 GW60.4%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar5742 MW
Batteries1150 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
PJMDominion GS-5 (Virginia SCC PUR-2025-00058) - ESAs signed on or after this date carry the 14-year term
From this date the GS-5 large-load tariff carries a 14-year minimum term, alongside the reported 85% of contracted transmission demand minimum and $1…
No date published yetdisputed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
Clover-Rawlings 500 kVSolar500 MWactive2019-12PJM
Clover 230kVCoal450 MWwithdrawn2007-07PJM
Clover 230kVCoal450 MWwithdrawn2007-07PJM
Clover 230kVCoal445 MWcompleted2012-10PJM
Clover 230 kVSolar300 MWwithdrawn2019-09PJM
SedgeHill - Person 230kVSolar195 MWwithdrawn2022-02PJM
SedgeHill - Person 230 kVSolar160 MWwithdrawn2021-07PJM
Clover 230 kVBatteries150 MWactive2021-03PJM
Crystal Hill - Perth 115 kVSolar149 MWwithdrawn2021-03PJM
Sedge Hill- Person 230kVSolar142 MWwithdrawn2022-03PJM
Halifax-Chase City 115 kVSolar120 MWwithdrawn2020-07PJM
Perth 115kVSolar100 MWwithdrawn2017-03PJM
Sedge Hill 230 kVBatteries100 MWwithdrawn2021-03PJM
Mount Laurel-Barnes Junction 115 kVSolar90 MWactive2020-08PJM
SedgeHill - Person 230 kVSolar90 MWwithdrawn2021-07PJM

How Halifax County compares

#419 in the US · #11 in VA

Halifax County ranks #419 of 1,607 US counties by power waiting to connect, and #11 of 71 in Virginia.

Common questions about power in Halifax County

How long does it take to get power for a data center in Halifax County, VA?

The median wait for a project still in the interconnection queue in Halifax County is 5.8 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 15 projects in Halifax County have reached energization and 32 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Halifax County, VA?

892 MW is currently requested across 6 active interconnection requests, and 1.3 GW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Halifax County, VA a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Virginia policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Halifax County — PJM — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Halifax County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Halifax County on the map County reports All of Virginia