Data centers and new power in Washington County, UT

780 MW of new power is waiting to connect to the grid in Washington County, UT — 4 active requests. Typical wait: 2.9 years. 3 projects are built, 27 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Washington County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Washington County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Washington County right now.

780 MW
of new power is waiting to connect
4 projects asked. Not yet approved. Roughly what 624,000 homes use.
186 MW
has actually been built
3 projects switched on so far.
2.9 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 9%
  • Still waiting 12%
  • Withdrawn 79%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Washington County.

What kind of power is asking to connect

  • Solar 38%
  • Natural gas 38%
  • Batteries 23%

By capacity requested. Data as of 14 October 2026.

All the numbers

34 requests ever filed
Pending applications
4
of 34 ever filed
Capacity queued
780 MW
requested, not committed
Already built
186 MW
3 projects connected
Built vs decided
10.0%
27 withdrawn
Median wait
2.9 yr
for applications still pending
Connected capacity
154 MW
indicator, see note

Source: interconnection queues published by PacifiCorp. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built3186 MW8.8%
Still waiting4780 MW11.8%
Withdrawn271.3 GW79.4%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar1300 MW
Natural gas1300 MW
Batteries2180 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
C1-39Solar300 MWactive2021-05PacifiCorp
PIS035Solar300 MWwithdrawn2023-05PacifiCorp
S0035Natural gas300 MWactive2025-04PacifiCorp
C3-113Solar240 MWwithdrawn2023-05PacifiCorp
337Hydro174 MWwithdrawn2010-06PacifiCorp
737Solar122 MWcompleted2016-04PacifiCorp
S0033Batteries122 MWactive2024-12PacifiCorp
35Wind100 MWwithdrawn2003-12PacifiCorp
474Wind80 MWwithdrawn2013-03PacifiCorp
641Solar58 MWcompleted2015-02PacifiCorp
S0014Batteries58 MWactive2022-11PacifiCorp
714Wind53 MWwithdrawn2015-10PacifiCorp
717Wind51 MWwithdrawn2015-11PacifiCorp
803Solar50 MWwithdrawn2016-09PacifiCorp
730Solar40 MWwithdrawn2016-03PacifiCorp

How Washington County compares

#479 in the US · #8 in UT

Washington County ranks #479 of 1,607 US counties by power waiting to connect, and #8 of 21 in Utah.

CountyWaitingCapacity queued
Miller276.5 GW
Utah County296.0 GW
Emery County193.5 GW
Juab County153.2 GW
Salt Lake County112.3 GW
Iron County111.8 GW
Kane County31.1 GW
Box Elder County5765 MW

Common questions about power in Washington County

How long does it take to get power for a data center in Washington County, UT?

The median wait for a project still in the interconnection queue in Washington County is 2.9 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 3 projects in Washington County have reached energization and 27 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Washington County, UT?

780 MW is currently requested across 4 active interconnection requests, and 186 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Washington County, UT a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Utah policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Washington County — PacifiCorp — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.