Data centers and new power in Providence County, RI

0 MW of new power is waiting to connect to the grid in Providence County, RI — 0 active requests. 13 projects are built, 36 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Providence County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Providence County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Providence County right now.

0 MW
of new power is waiting to connect
0 projects asked. Not yet approved.
1.3 GW
has actually been built
13 projects switched on so far.
36
projects gave up
Withdrawn before being built. Normal nationally.

Where every request ever filed here ended up

  • Built 27%
  • Withdrawn 73%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Providence County.

What kind of power is asking to connect

    By capacity requested. Data as of 14 October 2026.

    All the numbers

    49 requests ever filed
    Pending applications
    0
    of 49 ever filed
    Capacity queued
    0 MW
    requested, not committed
    Already built
    1.3 GW
    13 projects connected
    Built vs decided
    26.5%
    36 withdrawn

    Source: interconnection queues published by the transmission providers serving this county. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

    Outcome of every request filed here

    OutcomeProjectsCapacityShare
    Built131.3 GW26.5%
    Still waiting00 MW0.0%
    Withdrawn365.5 GW73.5%
    Paused0—0.0%

    Waiting to connect, by type of power

    Key dates for projects here

    no dated windows published
    QueueWhat closesClosesStanding
    FERCFERC large-load show cause — stakeholder comments on RTO responses
    Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
    No date published yetunconfirmed source
    FERCFERC RM26-4 — generic large-load rulemaking
    Still at ANOPR stage.
    No date published yetconfirmed source
    FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
    A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
    No date published yetconfirmed source

    A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

    The biggest projects on file

    top 15 by size
    ProjectTypeCapacityStatusFiledQueue
    Clear RiverNatural gas1.0 GWwithdrawn2015-01ISONE
    Combined Cycle CNRNatural gas1.0 GWwithdrawn2018-01ISONE
    Increase RISEC Winter CNRNatural gas613 MWcompleted2015-03ISONE
    Manchester Street Station increaseNatural gas471 MWcompleted2010-05ISONE
    Exciter UpgradesNatural gas441 MWwithdrawn2010-06ISONE
    Battery StorageBatteries415 MWwithdrawn2024-06ISONE
    Combined Cycle( see # 201)Natural gas320 MWwithdrawn2006-08ISONE
    Battery StorageBatteries305 MWwithdrawn2022-10ISONE
    Combustion Turbine GeneratorNatural gas238 MWwithdrawn2015-02ISONE
    Combustion TurbineNatural gas226 MWwithdrawn2015-02ISONE
    Combustion Turbine (Alt to Q523)Natural gas226 MWwithdrawn2015-02ISONE
    Battery StorageBatteries170 MWwithdrawn2021-12ISONE
    Battery StorageBatteries166 MWwithdrawn2024-05ISONE
    Converts QP 164 to combined cycle facility and incNatural gas162 MWwithdrawn2007-02ISONE
    Battery StorageBatteries109 MWwithdrawn2023-06ISONE

    How Providence County compares

    #1536 in the US · #4 in RI

    Providence County ranks #1536 of 1,607 US counties by power waiting to connect, and #4 of 4 in Rhode Island.

    CountyWaitingCapacity queued
    Washington County1205 MW
    Kent County00 MW
    Newport County00 MW

    Common questions about power in Providence County

    How long does it take to get power for a data center in Providence County, RI?

    We do not yet have a median wait for Providence County. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 13 projects in Providence County have reached energization and 36 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

    How much capacity is available in Providence County, RI?

    0 MW is currently requested across 0 active interconnection requests, and 1.3 GW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

    Is Providence County, RI a good site for a data center?

    This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Rhode Island policy page.

    Where does the data on this page come from?

    The interconnection queue published by the transmission providers serving Providence County — the utilities in this area — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

    Go deeper on Providence County

    The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.