Data centers and new power in Bronx County, NY
760 MW of new power is waiting to connect to the grid in Bronx County, NY — 5 active requests. Typical wait: 2.2 years. 0 projects are built, 11 withdrawn. Data as of 14 October 2026.
Is one near your house?
We have not mapped a large AI data center inside Bronx County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.
What is happening with electricity in Bronx County
Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Bronx County right now.
Where every request ever filed here ended up
Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Bronx County.
What kind of power is asking to connect
By capacity requested. Data as of 14 October 2026.
All the numbers
16 requests ever filed
Source: interconnection queues published by NYISO. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.
Outcome of every request filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 0 | 0 MW | 0.0% |
| Still waiting | 5 | 760 MW | 31.2% |
| Withdrawn | 11 | 3.3 GW | 68.8% |
| Paused | 0 | — | 0.0% |
Waiting to connect, by type of power
| Type | Projects | Capacity requested |
|---|---|---|
| Batteries | 5 | 760 MW |
Key dates for projects here
no dated windows published
| Queue | What closes | Closes | Standing |
|---|---|---|---|
| FERC | FERC large-load show cause — stakeholder comments on RTO responses Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70… | No date published yet | unconfirmed source |
| FERC | FERC RM26-4 — generic large-load rulemaking Still at ANOPR stage. | No date published yet | confirmed source |
| FERC | Georgia PSC - Georgia Power must file large-load contracts 30 days before execution A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed. | No date published yet | confirmed source |
| NYISO | NYISO cluster request window Class Year deliverability construct plus the new cluster process. | No date published yet | confirmed source |
A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.
The biggest projects on file
top 15 by size
| Project | Type | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| NY Wind - Mott Haven | Wind | 1.3 GW | withdrawn | 2020-08 | NYISO |
| Oak Point Yard | Natural gas | 500 MW | withdrawn | 1999-04 | NYISO |
| Blue Spruce Storage | Batteries | 300 MW | active | 2024-08 | NYISO |
| Tremont BESS | Batteries | 300 MW | withdrawn | 2020-08 | NYISO |
| Bronx Shores Energy Storage | Batteries | 300 MW | withdrawn | 2021-12 | NYISO |
| Palladium Storage | Batteries | 255 MW | withdrawn | 2023-02 | NYISO |
| Blue Spruce Storage | Batteries | 245 MW | withdrawn | 2023-05 | NYISO |
| Clover Leaf Hollers Ave | Natural gas | 174 MW | withdrawn | 2011-10 | NYISO |
| Palladium Storage | Batteries | 140 MW | active | 2024-08 | NYISO |
| Port Morris Energy Storage | Batteries | 130 MW | active | 2024-08 | NYISO |
| Harlem River Yards Energy Storage | Batteries | 106 MW | withdrawn | 2022-07 | NYISO |
| South Bronx Energy Storage | Batteries | 100 MW | active | 2024-09 | NYISO |
| Hell Gate Energy Storage | Batteries | 95 MW | withdrawn | 2022-07 | NYISO |
| Hell Gate Energy Storage | Batteries | 90 MW | active | 2024-10 | NYISO |
| Gotham Power - Bronx I | Natural gas | 80 MW | withdrawn | 2000-01 | NYISO |
How Bronx County compares
#486 in the US · #14 in NY
Bronx County ranks #486 of 1,607 US counties by power waiting to connect, and #14 of 57 in New York.
| County | Waiting | Capacity queued |
|---|---|---|
| Suffolk County | 27 | 3.7 GW |
| Kings County | 8 | 3.1 GW |
| Orange County | 10 | 1.6 GW |
| Ulster County | 11 | 1.3 GW |
| Steuben County | 8 | 1.3 GW |
| Dutchess County | 7 | 1.1 GW |
| Nassau County | 2 | 1.1 GW |
| Genesee County | 4 | 926 MW |
Common questions about power in Bronx County
How long does it take to get power for a data center in Bronx County, NY?
The median wait for a project still in the interconnection queue in Bronx County is 2.2 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 0 projects in Bronx County have reached energization and 11 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.
How much capacity is available in Bronx County, NY?
760 MW is currently requested across 5 active interconnection requests, and 0 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.
Is Bronx County, NY a good site for a data center?
This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our New York policy page.
Where does the data on this page come from?
The interconnection queue published by the transmission providers serving Bronx County — NYISO — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.
Go deeper on Bronx County
The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.