Data centers and new power in Morton County, ND

450 MW of new power is waiting to connect to the grid in Morton County, ND — 4 active requests. Typical wait: 4.6 years. 2 projects are built, 10 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Morton County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Morton County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Morton County right now.

450 MW
of new power is waiting to connect
4 projects asked. Not yet approved. Roughly what 360,000 homes use.
118 MW
has actually been built
2 projects switched on so far.
4.6 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 12%
  • Still waiting 25%
  • Withdrawn 62%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Morton County.

What kind of power is asking to connect

  • Wind 100%

By capacity requested. Data as of 14 October 2026.

All the numbers

16 requests ever filed
Pending applications
4
of 16 ever filed
Capacity queued
450 MW
requested, not committed
Already built
118 MW
2 projects connected
Built vs decided
16.7%
10 withdrawn
Median wait
4.6 yr
for applications still pending
Connected capacity
994 MW
indicator, see note

Source: interconnection queues published by MISO. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built2118 MW12.5%
Still waiting4450 MW25.0%
Withdrawn102.1 GW62.5%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Wind4450 MW

Key dates for projects here

1 dated · next closes 2027-09-10 (MISO)
QueueWhat closesClosesStanding
MISOMISO DPP-2026 Definitive Planning Phase application deadline
Attachment X of the tariff and BPM-015.
2027-09-10confirmed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
Mandan 230 kVWind500 MWwithdrawn2021-11MISO
GEN-2023-054Solar400 MWwithdrawn2023-10SPP
GI-0911Wind400 MWwithdrawn2009-04WAPA-IS
GEN-2017-056Wind210 MWwithdrawn2017-05SPP
Mandan BN-Northwest Mandan 115kV LineSolar200 MWwithdrawn2020-06MISO
Square Butte 230 kV Substation EastWind150 MWactive2022-09MISO
GI-0926Wind110 MWcompleted2009-10WAPA-IS
Heskitt 115 kV SwitchyardNatural gas103 MWwithdrawn2019-04MISO
Mandan 230 kVSolar100 MWwithdrawn2021-08MISO
Tri-County 230 kV SubstationWind100 MWactive2021-08MISO
Tri-county 230 kV substationWind100 MWwithdrawn2017-06MISO
Tri-county 230kV subWind100 MWwithdrawn2017-06MISO
Tri-County 230 kV SubstationWind100 MWactive2021-08MISO
Square Butte 230 kV Substation EastWind100 MWactive2022-09MISO
GI-0614bOther10 MWwithdrawn2006-09WAPA-IS

How Morton County compares

#664 in the US · #4 in ND

Morton County ranks #664 of 1,607 US counties by power waiting to connect, and #4 of 17 in North Dakota.

CountyWaitingCapacity queued
Williams County52.2 GW
Cass County41.1 GW
Mercer County3534 MW
Stutsman County2447 MW
Oliver County2404 MW
Ward County3400 MW
Stark County2332 MW
Dickey County1300 MW

Common questions about power in Morton County

How long does it take to get power for a data center in Morton County, ND?

The median wait for a project still in the interconnection queue in Morton County is 4.6 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 2 projects in Morton County have reached energization and 10 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Morton County, ND?

450 MW is currently requested across 4 active interconnection requests, and 118 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Morton County, ND a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our North Dakota policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Morton County — MISO — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.