Data centers and new power in Cass County, ND
1.1 GW of new power is waiting to connect to the grid in Cass County, ND — 4 active requests. Typical wait: 2.3 years. 1 projects are built, 13 withdrawn. Data as of 14 October 2026.
Is one near your house?
We have not mapped a large AI data center inside Cass County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.
What is happening with electricity in Cass County
Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Cass County right now.
Where every request ever filed here ended up
Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Cass County.
What kind of power is asking to connect
By capacity requested. Data as of 14 October 2026.
All the numbers
18 requests ever filed
Source: interconnection queues published by MISO. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.
Outcome of every request filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 1 | 200 MW | 5.6% |
| Still waiting | 4 | 1.1 GW | 22.2% |
| Withdrawn | 13 | 2.7 GW | 72.2% |
| Paused | 0 | — | 0.0% |
Waiting to connect, by type of power
| Type | Projects | Capacity requested |
|---|---|---|
| Solar + battery | 1 | 481 MW |
| Solar | 2 | 400 MW |
| Wind | 1 | 200 MW |
Key dates for projects here
1 dated · next closes 2027-09-10 (MISO)
| Queue | What closes | Closes | Standing |
|---|---|---|---|
| MISO | MISO DPP-2026 Definitive Planning Phase application deadline Attachment X of the tariff and BPM-015. | 2027-09-10 | confirmed source |
| FERC | FERC large-load show cause — stakeholder comments on RTO responses Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70… | No date published yet | unconfirmed source |
| FERC | FERC RM26-4 — generic large-load rulemaking Still at ANOPR stage. | No date published yet | confirmed source |
| FERC | Georgia PSC - Georgia Power must file large-load contracts 30 days before execution A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed. | No date published yet | confirmed source |
A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.
The biggest projects on file
top 15 by size
| Project | Type | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| BISON | Solar + battery | 481 MW | active | 2022-07 | MISO |
| Bison Substation 345 kV | Wind | 400 MW | withdrawn | 2020-06 | MISO |
| Buffalo 345 kV Substation | Solar + battery | 250 MW | withdrawn | 2025-10 | MISO |
| Buffalo 345 kV Substation | Solar + battery | 250 MW | withdrawn | 2025-10 | MISO |
| Bison 345kV Substation | Wind | 207 MW | withdrawn | 2018-03 | MISO |
| Buffalo 115 kV | Wind | 200 MW | active | 2024-10 | MISO |
| Bison | Solar | 200 MW | active | 2024-03 | MISO |
| Bison 345 kV Substation | Solar | 200 MW | withdrawn | 2018-03 | MISO |
| Buffalo 345kV Substation | Solar | 200 MW | withdrawn | 2019-04 | MISO |
| Bison 345kV Substation | Solar | 200 MW | withdrawn | 2017-06 | MISO |
| Bison-Alexandria 345kV | Solar | 200 MW | withdrawn | 2020-06 | MISO |
| BISON | Solar | 200 MW | completed | 2024-04 | MISO |
| Bison 345kV Substation | Wind | 200 MW | withdrawn | 2017-06 | MISO |
| Bison 345 kV | Solar | 200 MW | withdrawn | 2022-06 | MISO |
| BISON | Solar | 200 MW | active | 2025-03 | MISO |
How Cass County compares
#350 in the US · #2 in ND
Cass County ranks #350 of 1,607 US counties by power waiting to connect, and #2 of 17 in North Dakota.
| County | Waiting | Capacity queued |
|---|---|---|
| Williams County | 5 | 2.2 GW |
| Mercer County | 3 | 534 MW |
| Morton County | 4 | 450 MW |
| Stutsman County | 2 | 447 MW |
| Oliver County | 2 | 404 MW |
| Ward County | 3 | 400 MW |
| Stark County | 2 | 332 MW |
| Dickey County | 1 | 300 MW |
Common questions about power in Cass County
How long does it take to get power for a data center in Cass County, ND?
The median wait for a project still in the interconnection queue in Cass County is 2.3 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 1 projects in Cass County have reached energization and 13 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.
How much capacity is available in Cass County, ND?
1.1 GW is currently requested across 4 active interconnection requests, and 200 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.
Is Cass County, ND a good site for a data center?
This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our North Dakota policy page.
Where does the data on this page come from?
The interconnection queue published by the transmission providers serving Cass County — MISO — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.