Data centers and new power in Cass County, ND

1.1 GW of new power is waiting to connect to the grid in Cass County, ND — 4 active requests. Typical wait: 2.3 years. 1 projects are built, 13 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Cass County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Cass County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Cass County right now.

1.1 GW
of new power is waiting to connect
4 projects asked. Not yet approved. Roughly what 865,000 homes use.
200 MW
has actually been built
1 projects switched on so far.
2.3 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 6%
  • Still waiting 22%
  • Withdrawn 72%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Cass County.

What kind of power is asking to connect

  • Solar + battery 44%
  • Solar 37%
  • Wind 19%

By capacity requested. Data as of 14 October 2026.

All the numbers

18 requests ever filed
Pending applications
4
of 18 ever filed
Capacity queued
1.1 GW
requested, not committed
Already built
200 MW
1 projects connected
Built vs decided
7.1%
13 withdrawn
Median wait
2.3 yr
for applications still pending
Connected capacity
4 MW
indicator, see note

Source: interconnection queues published by MISO. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built1200 MW5.6%
Still waiting41.1 GW22.2%
Withdrawn132.7 GW72.2%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar + battery1481 MW
Solar2400 MW
Wind1200 MW

Key dates for projects here

1 dated · next closes 2027-09-10 (MISO)
QueueWhat closesClosesStanding
MISOMISO DPP-2026 Definitive Planning Phase application deadline
Attachment X of the tariff and BPM-015.
2027-09-10confirmed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
BISONSolar + battery481 MWactive2022-07MISO
Bison Substation 345 kVWind400 MWwithdrawn2020-06MISO
Buffalo 345 kV SubstationSolar + battery250 MWwithdrawn2025-10MISO
Buffalo 345 kV SubstationSolar + battery250 MWwithdrawn2025-10MISO
Bison 345kV SubstationWind207 MWwithdrawn2018-03MISO
Buffalo 115 kVWind200 MWactive2024-10MISO
BisonSolar200 MWactive2024-03MISO
Bison 345 kV SubstationSolar200 MWwithdrawn2018-03MISO
Buffalo 345kV SubstationSolar200 MWwithdrawn2019-04MISO
Bison 345kV SubstationSolar200 MWwithdrawn2017-06MISO
Bison-Alexandria 345kVSolar200 MWwithdrawn2020-06MISO
BISONSolar200 MWcompleted2024-04MISO
Bison 345kV SubstationWind200 MWwithdrawn2017-06MISO
Bison 345 kVSolar200 MWwithdrawn2022-06MISO
BISONSolar200 MWactive2025-03MISO

How Cass County compares

#350 in the US · #2 in ND

Cass County ranks #350 of 1,607 US counties by power waiting to connect, and #2 of 17 in North Dakota.

CountyWaitingCapacity queued
Williams County52.2 GW
Mercer County3534 MW
Morton County4450 MW
Stutsman County2447 MW
Oliver County2404 MW
Ward County3400 MW
Stark County2332 MW
Dickey County1300 MW

Common questions about power in Cass County

How long does it take to get power for a data center in Cass County, ND?

The median wait for a project still in the interconnection queue in Cass County is 2.3 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 1 projects in Cass County have reached energization and 13 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Cass County, ND?

1.1 GW is currently requested across 4 active interconnection requests, and 200 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Cass County, ND a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our North Dakota policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Cass County — MISO — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Cass County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Cass County on the map County reports All of North Dakota