Data centers and new power in Cascade County, MT

70 MW of new power is waiting to connect to the grid in Cascade County, MT — 1 active requests. Typical wait: 3.9 years. 7 projects are built, 38 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Cascade County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Cascade County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Cascade County right now.

70 MW
of new power is waiting to connect
1 projects asked. Not yet approved. Roughly what 56,000 homes use.
54 MW
has actually been built
7 projects switched on so far.
3.9 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 15%
  • Still waiting 2%
  • Withdrawn 83%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Cascade County.

What kind of power is asking to connect

  • Hydro 100%

By capacity requested. Data as of 14 October 2026.

All the numbers

46 requests ever filed
Pending applications
1
of 46 ever filed
Capacity queued
70 MW
requested, not committed
Already built
54 MW
7 projects connected
Built vs decided
15.6%
38 withdrawn
Median wait
3.9 yr
for applications still pending
Connected capacity
331 MW
indicator, see note

Source: interconnection queues published by NWMT. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built754 MW15.2%
Still waiting170 MW2.2%
Withdrawn382.4 GW82.6%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Hydro170 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
429Solar300 MWwithdrawn2022-06NWMT
7Natural gas280 MWwithdrawn2001-05NWMT
53Natural gas277 MWwithdrawn2006-12NWMT
32Coal268 MWwithdrawn2004-07NWMT
380Solar225 MWwithdrawn2020-06NWMT
388Solar200 MWwithdrawn2020-07NWMT
460Solar150 MWwithdrawn2024-05NWMT
98Wind150 MWwithdrawn2008-09NWMT
94Natural gas128 MWwithdrawn2008-07NWMT
103Natural gas120 MWwithdrawn2009-02NWMT
437Hydro70 MWactive2022-12NWMT
83Hydro52 MWwithdrawn2008-03NWMT
82Hydro49 MWwithdrawn2008-03NWMT
113Wind40 MWwithdrawn2009-12NWMT
158Wind24 MWwithdrawn2012-09NWMT

How Cascade County compares

#1159 in the US · #8 in MT

Cascade County ranks #1159 of 1,607 US counties by power waiting to connect, and #8 of 29 in Montana.

Common questions about power in Cascade County

How long does it take to get power for a data center in Cascade County, MT?

The median wait for a project still in the interconnection queue in Cascade County is 3.9 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 7 projects in Cascade County have reached energization and 38 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Cascade County, MT?

70 MW is currently requested across 1 active interconnection requests, and 54 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Cascade County, MT a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Montana policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Cascade County — NWMT — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Cascade County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Cascade County on the map County reports All of Montana