Data centers and new power in Big Horn County, MT

608 MW of new power is waiting to connect to the grid in Big Horn County, MT — 3 active requests. Typical wait: 2.9 years. 2 projects are built, 22 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Big Horn County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Big Horn County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Big Horn County right now.

608 MW
of new power is waiting to connect
3 projects asked. Not yet approved. Roughly what 486,000 homes use.
112 MW
has actually been built
2 projects switched on so far.
2.9 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 7%
  • Still waiting 11%
  • Withdrawn 81%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Big Horn County.

What kind of power is asking to connect

  • Solar 99%
  • Hydro 1%

By capacity requested. Data as of 14 October 2026.

All the numbers

27 requests ever filed
Pending applications
3
of 27 ever filed
Capacity queued
608 MW
requested, not committed
Already built
112 MW
2 projects connected
Built vs decided
8.3%
22 withdrawn
Median wait
2.9 yr
for applications still pending
Connected capacity
397 MW
indicator, see note

Source: interconnection queues published by NWMT, PacifiCorp, SPP. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built2112 MW7.4%
Still waiting3608 MW11.1%
Withdrawn221.6 GW81.5%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar2600 MW
Hydro18 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source
SPPSPP 2028 CPP Interconnection Cluster Study (ICS) application window
Definitive Interconnection System Impact Study cluster, post Order 2023 compliance.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
ASGI-2024-012Solar300 MWactive—SPP
419Solar300 MWactive2022-02NWMT
937Wind250 MWwithdrawn2017-08PacifiCorp
430Solar200 MWwithdrawn2022-07NWMT
459Solar200 MWwithdrawn2024-05NWMT
5Coal109 MWcompleted2001-04NWMT
GI-0306Coal109 MWwithdrawn2003-04WAPA-IS
100-AWind99 MWwithdrawn2006-11PacifiCorp
100-BWind99 MWwithdrawn2006-11PacifiCorp
428Solar80 MWwithdrawn2022-05NWMT
1089Solar80 MWwithdrawn2018-11PacifiCorp
1090Solar80 MWwithdrawn2018-11PacifiCorp
1091Solar80 MWwithdrawn2018-11PacifiCorp
168Wind78 MWwithdrawn2007-10PacifiCorp
208Wind78 MWwithdrawn2008-03PacifiCorp

How Big Horn County compares

#552 in the US · #5 in MT

Big Horn County ranks #552 of 1,607 US counties by power waiting to connect, and #5 of 29 in Montana.

Common questions about power in Big Horn County

How long does it take to get power for a data center in Big Horn County, MT?

The median wait for a project still in the interconnection queue in Big Horn County is 2.9 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 2 projects in Big Horn County have reached energization and 22 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Big Horn County, MT?

608 MW is currently requested across 3 active interconnection requests, and 112 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Big Horn County, MT a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Montana policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Big Horn County — NWMT, PacifiCorp, SPP — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Big Horn County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.