Data centers and new power in Allen County, IN
400 MW of new power is waiting to connect to the grid in Allen County, IN — 5 active requests. Typical wait: 6.0 years. 0 projects are built, 16 withdrawn. Data as of 14 October 2026.
How far is it from your house?
Google Fort Wayne, run by Google, is in Allen County.
44 public schools are within 5 miles of it, 3 within one mile. Counted from the facility, not from any home. School list: US Department of Education.
What is happening with electricity in Allen County
Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Allen County right now.
Where every request ever filed here ended up
Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Allen County.
What kind of power is asking to connect
By capacity requested. Data as of 14 October 2026.
All the numbers
21 requests ever filed
Source: interconnection queues published by PJM. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.
Outcome of every request filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 0 | 0 MW | 0.0% |
| Still waiting | 5 | 400 MW | 23.8% |
| Withdrawn | 16 | 1.9 GW | 76.2% |
| Paused | 0 | — | 0.0% |
Waiting to connect, by type of power
| Type | Projects | Capacity requested |
|---|---|---|
| Solar | 3 | 300 MW |
| Batteries | 2 | 100 MW |
Key dates for projects here
no dated windows published
| Queue | What closes | Closes | Standing |
|---|---|---|---|
| PJM | Dominion GS-5 (Virginia SCC PUR-2025-00058) - ESAs signed on or after this date carry the 14-year term From this date the GS-5 large-load tariff carries a 14-year minimum term, alongside the reported 85% of contracted transmission demand minimum and $1… | No date published yet | disputed source |
| FERC | FERC large-load show cause — stakeholder comments on RTO responses Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70… | No date published yet | unconfirmed source |
| FERC | FERC RM26-4 — generic large-load rulemaking Still at ANOPR stage. | No date published yet | confirmed source |
| FERC | Georgia PSC - Georgia Power must file large-load contracts 30 days before execution A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed. | No date published yet | confirmed source |
A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.
The biggest projects on file
top 15 by size
| Project | Type | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| Convoy-East Lima 345kV | Wind | 240 MW | withdrawn | 2007-07 | PJM |
| Lincoln-North Delphos | Wind | 200 MW | withdrawn | 2007-07 | PJM |
| Allen - RP Mone 345 kV | Solar | 180 MW | withdrawn | 2021-09 | PJM |
| Allen - RP Mone 345 kV | Solar | 180 MW | withdrawn | 2023-03 | PJM |
| Haviland-Tillman 138kV | Wind | 100 MW | withdrawn | 2006-06 | PJM |
| Allen 345 kV | Solar | 100 MW | active | 2020-03 | PJM |
| Allen 345 kV | Solar | 100 MW | active | 2020-09 | PJM |
| Tillman 138 kV | Solar | 100 MW | active | 2020-09 | PJM |
| Sowers 138 kV | Solar | 100 MW | withdrawn | 2020-09 | PJM |
| Allen 345 kV | Solar | 100 MW | withdrawn | 2021-03 | PJM |
| Allen 345 kV | Solar | 100 MW | withdrawn | 2021-03 | PJM |
| Sowers 138 kV | Solar | 100 MW | withdrawn | 2021-03 | PJM |
| Coventry 138 kV | Batteries | 100 MW | withdrawn | 2021-09 | PJM |
| Milan 138 kV | Batteries | 100 MW | withdrawn | 2021-09 | PJM |
| Wayne Trace 138 kV | Batteries | 100 MW | withdrawn | 2021-09 | PJM |
How Allen County compares
#698 in the US · #19 in IN
Allen County ranks #698 of 1,607 US counties by power waiting to connect, and #19 of 57 in Indiana.
| County | Waiting | Capacity queued |
|---|---|---|
| Sullivan County | 20 | 6.4 GW |
| Pulaski County | 10 | 3.2 GW |
| Vermillion County | 4 | 2.4 GW |
| White County | 13 | 2.1 GW |
| Fountain County | 4 | 1.4 GW |
| Blackford County | 7 | 1.3 GW |
| St. Joseph County | 4 | 1.2 GW |
| Greene County | 6 | 1.2 GW |
Common questions about power in Allen County
How long does it take to get power for a data center in Allen County, IN?
The median wait for a project still in the interconnection queue in Allen County is 6.0 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 0 projects in Allen County have reached energization and 16 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.
How much capacity is available in Allen County, IN?
400 MW is currently requested across 5 active interconnection requests, and 0 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.
Is Allen County, IN a good site for a data center?
This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Indiana policy page.
Where does the data on this page come from?
The interconnection queue published by the transmission providers serving Allen County — PJM — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.
Go deeper on Allen County
The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.