Data centers and new power in Heard County, GA

4.2 GW of new power is waiting to connect to the grid in Heard County, GA — 7 active requests. Typical wait: 2.6 years. 2 projects are built, 4 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Heard County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Heard County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Heard County right now.

4.2 GW
of new power is waiting to connect
7 projects asked. Not yet approved. Roughly what 3.4 million homes use.
178 MW
has actually been built
2 projects switched on so far.
2.6 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 14%
  • Still waiting 50%
  • Withdrawn 29%
  • Paused 7%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Heard County.

What kind of power is asking to connect

  • Natural gas 88%
  • Batteries 12%

By capacity requested. Data as of 14 October 2026.

All the numbers

14 requests ever filed
Pending applications
7
of 14 ever filed
Capacity queued
4.2 GW
requested, not committed
Already built
178 MW
2 projects connected
Built vs decided
33.3%
4 withdrawn
Median wait
2.6 yr
for applications still pending
Connected capacity
4.0 GW
indicator, see note

Source: interconnection queues published by SOCO. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built2178 MW14.3%
Still waiting74.2 GW50.0%
Withdrawn43.1 GW28.6%
Paused1—7.1%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Natural gas63.7 GW
Batteries1500 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
SoCo-Wansley CC'sNatural gas1.2 GWcompleted—SOCO
IC-206Natural gas1.2 GWwithdrawn2003-09SOCO
25-IC-BHNatural gas1.0 GWwithdrawn—SOCO
IC-1254aNatural gas1.0 GWactive2024-03SOCO
IC-1254bNatural gas1.0 GWactive2024-03SOCO
Tenaska Heard Co.Natural gas900 MWcompleted—SOCO
IC-1263Natural gas722 MWactive2024-03SOCO
IC-1264Natural gas722 MWactive2024-03SOCO
IC-1247Batteries500 MWactive2024-03SOCO
IC-1261Natural gas419 MWwithdrawn2024-03SOCO
IC-1262Natural gas419 MWwithdrawn2024-03SOCO
25-IC-1333ANatural gas129 MWactive2025-04SOCO
25-IC-1333BNatural gas129 MWactive2025-04SOCO
Hawk Road (aka Dynegy)Natural gas100 MWcompleted2023-12GTC
IC-1035Solar100 MWsuspended2022-05SOCO

How Heard County compares

#69 in the US · #1 in GA

Heard County ranks #69 of 1,607 US counties by power waiting to connect, and #1 of 61 in Georgia.

CountyWaitingCapacity queued
Bartow County73.6 GW
Coweta County62.6 GW
Mitchell County62.4 GW
Monroe County12.0 GW
Hancock County42.0 GW
Effingham County131.9 GW
Sumter County51.4 GW
Laurens County71.3 GW

Common questions about power in Heard County

How long does it take to get power for a data center in Heard County, GA?

The median wait for a project still in the interconnection queue in Heard County is 2.6 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 2 projects in Heard County have reached energization and 4 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Heard County, GA?

4.2 GW is currently requested across 7 active interconnection requests, and 178 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Heard County, GA a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Georgia policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Heard County — SOCO — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Heard County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Heard County on the map County reports All of Georgia