Data centers and new power in La Paz County, AZ
5.8 GW of new power is waiting to connect to the grid in La Paz County, AZ — 7 active requests. Typical wait: 4.7 years. 1 projects are built, 18 withdrawn. Data as of 14 October 2026.
Is one near your house?
We have not mapped a large AI data center inside La Paz County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.
What is happening with electricity in La Paz County
Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in La Paz County right now.
Where every request ever filed here ended up
Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for La Paz County.
What kind of power is asking to connect
By capacity requested. Data as of 14 October 2026.
All the numbers
26 requests ever filed
Source: interconnection queues published by CAISO, WAPA-DSW. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.
Outcome of every request filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 1 | 500 MW | 3.8% |
| Still waiting | 7 | 5.8 GW | 26.9% |
| Withdrawn | 18 | 6.0 GW | 69.2% |
| Paused | 0 | — | 0.0% |
Waiting to connect, by type of power
| Type | Projects | Capacity requested |
|---|---|---|
| Solar + battery | 3 | 4.5 GW |
| Solar | 3 | 750 MW |
| Natural gas | 1 | 453 MW |
Key dates for projects here
1 dated · next closes 2026-10-15 (CAISO)
| Queue | What closes | Closes | Standing |
|---|---|---|---|
| CAISO | CAISO Cluster 16 interconnection request window Interconnection requests submitted through the GRIP portal. | 2026-10-15 | confirmed source |
| FERC | FERC large-load show cause — stakeholder comments on RTO responses Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70… | No date published yet | unconfirmed source |
| FERC | FERC RM26-4 — generic large-load rulemaking Still at ANOPR stage. | No date published yet | confirmed source |
| FERC | Georgia PSC - Georgia Power must file large-load contracts 30 days before execution A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed. | No date published yet | confirmed source |
A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.
The biggest projects on file
top 15 by size
| Project | Type | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| ATLAS COMPLEX | Solar + battery | 3.2 GW | active | 2017-05 | CAISO |
| Withdrawn project | Solar + battery | 2.0 GW | withdrawn | 2021-04 | CAISO |
| BOUSE SOLAR AND STORAGE PLANT | Solar + battery | 1.0 GW | active | 2021-04 | CAISO |
| Withdrawn project | Solar | 900 MW | withdrawn | 2008-05 | CAISO |
| Withdrawn project | Solar + battery | 700 MW | withdrawn | 2021-04 | CAISO |
| CENTENNIAL FLATS | Solar + battery | 500 MW | completed | 2018-04 | CAISO |
| Withdrawn project | Solar + battery | 500 MW | withdrawn | 2021-04 | CAISO |
| 2023-G13 | Natural gas | 453 MW | active | 2023-10 | WAPA-DSW |
| SOCORRO PEAK SOLAR | Solar + battery | 350 MW | active | 2021-04 | CAISO |
| Withdrawn project | Solar | 350 MW | withdrawn | 2021-04 | CAISO |
| Q69 | Solar | 300 MW | withdrawn | 2009-06 | APS |
| Withdrawn project | Solar | 250 MW | withdrawn | 2008-05 | CAISO |
| Withdrawn project | Solar | 250 MW | withdrawn | 2008-06 | CAISO |
| Q523 | Solar | 250 MW | withdrawn | 2023-03 | APS |
| 2022-G1 | Solar | 250 MW | active | 2022-01 | WAPA-DSW |
How La Paz County compares
#45 in the US · #6 in AZ
La Paz County ranks #45 of 1,607 US counties by power waiting to connect, and #6 of 10 in Arizona.
| County | Waiting | Capacity queued |
|---|---|---|
| Maricopa County | 91 | 25.2 GW |
| Navajo County | 25 | 9.4 GW |
| Mohave County | 22 | 7.8 GW |
| Coconino County | 13 | 7.8 GW |
| Yuma County | 23 | 7.3 GW |
| Pima County | 19 | 4.9 GW |
| Apache County | 10 | 3.9 GW |
| Yavapai County | 5 | 1.5 GW |
Common questions about power in La Paz County
How long does it take to get power for a data center in La Paz County, AZ?
The median wait for a project still in the interconnection queue in La Paz County is 4.7 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 1 projects in La Paz County have reached energization and 18 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.
How much capacity is available in La Paz County, AZ?
5.8 GW is currently requested across 7 active interconnection requests, and 500 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.
Is La Paz County, AZ a good site for a data center?
This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Arizona policy page.
Where does the data on this page come from?
The interconnection queue published by the transmission providers serving La Paz County — CAISO, WAPA-DSW — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.
Go deeper on La Paz County
The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.