Data centers and new power in Platte County, WY

3.4 GW of new power is waiting to connect to the grid in Platte County, WY — 12 active requests. Typical wait: 3.4 years. 1 projects are built, 13 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Platte County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Platte County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Platte County right now.

3.4 GW
of new power is waiting to connect
12 projects asked. Not yet approved. Roughly what 2.7 million homes use.
5 MW
has actually been built
1 projects switched on so far.
3.4 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 4%
  • Still waiting 46%
  • Withdrawn 50%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Platte County.

What kind of power is asking to connect

  • Solar 49%
  • Wind 27%
  • Solar + battery 24%

By capacity requested. Data as of 14 October 2026.

All the numbers

26 requests ever filed
Pending applications
12
of 26 ever filed
Capacity queued
3.4 GW
requested, not committed
Already built
5 MW
1 projects connected
Built vs decided
7.1%
13 withdrawn
Median wait
3.4 yr
for applications still pending
Connected capacity
1.9 GW
indicator, see note

Source: interconnection queues published by CLPT, SPP, TSGT. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built15 MW3.8%
Still waiting123.4 GW46.2%
Withdrawn136.7 GW50.0%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar51.7 GW
Wind6900 MW
Solar + battery1800 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source
SPPSPP 2028 CPP Interconnection Cluster Study (ICS) application window
Definitive Interconnection System Impact Study cluster, post Order 2023 compliance.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
Withdrawn projectWind3.0 GWwithdrawn2011-03CAISO
GI-CS-2025-25Solar + battery800 MWactive2025-10SPP
GI-CS-2025-25Solar800 MWactive2025-10TSGT
927Wind600 MWwithdrawn2017-08PacifiCorp
930Wind400 MWwithdrawn2017-08PacifiCorp
931Wind400 MWwithdrawn2017-08PacifiCorp
932Wind400 MWwithdrawn2017-08PacifiCorp
CLPT G16Solar300 MWactive2022-04CLPT
925Wind300 MWwithdrawn2017-08PacifiCorp
926Wind300 MWwithdrawn2017-08PacifiCorp
928Wind300 MWwithdrawn2017-08PacifiCorp
929Wind300 MWwithdrawn2017-08PacifiCorp
2003-03-01 00:00:00Solar200 MWactive2025-07CLPT
2004-03-01 00:00:00Solar200 MWactive2025-07CLPT
GI-1002Wind200 MWwithdrawn2010-01WAPA-IS

How Platte County compares

#98 in the US · #2 in WY

Platte County ranks #98 of 1,607 US counties by power waiting to connect, and #2 of 12 in Wyoming.

CountyWaitingCapacity queued
Laramie County225.4 GW
Carbon/Albany162.7 GW
Converse County102.3 GW
Lincoln County51.8 GW
Sweetwater County21.2 GW
Albany County5964 MW
Campbell County3590 MW
Natrona County4409 MW

Common questions about power in Platte County

How long does it take to get power for a data center in Platte County, WY?

The median wait for a project still in the interconnection queue in Platte County is 3.4 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 1 projects in Platte County have reached energization and 13 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Platte County, WY?

3.4 GW is currently requested across 12 active interconnection requests, and 5 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Platte County, WY a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Wyoming policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Platte County — CLPT, SPP, TSGT — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Platte County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Platte County on the map County reports All of Wyoming