Data centers and new power in Addison County, VT

50 MW of new power is waiting to connect to the grid in Addison County, VT — 1 active requests. Typical wait: 7.8 years. 0 projects are built, 7 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Addison County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Addison County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Addison County right now.

50 MW
of new power is waiting to connect
1 projects asked. Not yet approved. Roughly what 40,000 homes use.
0 MW
has actually been built
0 projects switched on so far.
7.8 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Still waiting 12%
  • Withdrawn 88%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Addison County.

What kind of power is asking to connect

  • Solar 100%

By capacity requested. Data as of 14 October 2026.

All the numbers

8 requests ever filed
Pending applications
1
of 8 ever filed
Capacity queued
50 MW
requested, not committed
Already built
0 MW
0 projects connected
Built vs decided
0.0%
7 withdrawn
Median wait
7.8 yr
for applications still pending
Connected capacity
46 MW
indicator, see note

Source: interconnection queues published by ISONE. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built00 MW0.0%
Still waiting150 MW12.5%
Withdrawn71.9 GW87.5%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar150 MW

Key dates for projects here

1 dated · next closes 2026-11-19 (ISONE)
QueueWhat closesClosesStanding
ISONEISO-NE cluster request window
Cluster study under OATT Schedules 22, 23 and 25.
2026-11-19disputed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 8 by size
ProjectTypeCapacityStatusFiledQueue
HVDC Tie - Import onlyNuclear1.0 GWwithdrawn2015-02ISONE
HVDC Tie - Import onlyNuclear425 MWwithdrawn2015-02ISONE
controllable 150 kV HVDC Tie - Import OnlyNuclear400 MWwithdrawn2018-09ISONE
FPS Panton SolarSolar50 MWactive2018-12ISONE
Solar CNR onlySolar50 MWwithdrawn2024-04ISONE
Battery StorageBatteries20 MWwithdrawn2021-04ISONE
1000 MW HVDC Tie V3 (See Q425)Nuclear—withdrawn2013-10ISONE
425 MW HVDC TieNuclear—withdrawn2014-05ISONE

How Addison County compares

#1174 in the US · #1 in VT

Addison County ranks #1174 of 1,607 US counties by power waiting to connect, and #1 of 9 in Vermont.

Common questions about power in Addison County

How long does it take to get power for a data center in Addison County, VT?

The median wait for a project still in the interconnection queue in Addison County is 7.8 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 0 projects in Addison County have reached energization and 7 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Addison County, VT?

50 MW is currently requested across 1 active interconnection requests, and 0 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Addison County, VT a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Vermont policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Addison County — ISONE — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Addison County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Addison County on the map County reports All of Vermont