Data centers and new power in Champaign County, IL

1.1 GW of new power is waiting to connect to the grid in Champaign County, IL — 7 active requests. Typical wait: 2.5 years. 1 projects are built, 7 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Champaign County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Champaign County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Champaign County right now.

1.1 GW
of new power is waiting to connect
7 projects asked. Not yet approved. Roughly what 892,000 homes use.
150 MW
has actually been built
1 projects switched on so far.
2.5 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 7%
  • Still waiting 47%
  • Withdrawn 47%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Champaign County.

What kind of power is asking to connect

  • Solar 62%
  • Wind 26%
  • Solar + battery 12%

By capacity requested. Data as of 14 October 2026.

All the numbers

15 requests ever filed
Pending applications
7
of 15 ever filed
Capacity queued
1.1 GW
requested, not committed
Already built
150 MW
1 projects connected
Built vs decided
12.5%
7 withdrawn
Median wait
2.5 yr
for applications still pending
Connected capacity
272 MW
indicator, see note

Source: interconnection queues published by MISO. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built1150 MW6.7%
Still waiting71.1 GW46.7%
Withdrawn71.2 GW46.7%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar4691 MW
Wind2288 MW
Solar + battery1135 MW

Key dates for projects here

1 dated · next closes 2027-09-10 (MISO)
QueueWhat closesClosesStanding
MISOMISO DPP-2026 Definitive Planning Phase application deadline
Attachment X of the tariff and BPM-015.
2027-09-10confirmed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
RisingSolar300 MWactive2024-04MISO
7BUNSONVILLE - 7SIDNEY 345.0kVWind300 MWwithdrawn2024-04MISO
4WEEDMAN - 4MAHOMET 1 138.0kVSolar + battery215 MWwithdrawn2024-04MISO
Rising 345kVSolar200 MWwithdrawn2020-06MISO
RisingSolar191 MWactive2024-04MISO
4SIDNEY 1 - 4MIRA TAP 138.0kVSolar160 MWwithdrawn2022-03MISO
Sidney Substation 138 kV BusSolar150 MWcompleted2018-03MISO
Rantoul East 138kVWind150 MWactive2022-03MISO
4RANTOUL - 4RISING 138.0kVWind138 MWactive2025-02MISO
4RANTOUL - 4RISING 138.0kVWind137 MWwithdrawn2024-04MISO
Sidney 138 kVSolar + battery135 MWactive2022-09MISO
Sidney 138kVSolar116 MWwithdrawn2021-12MISO
RisingSolar100 MWactive2021-08MISO
RisingSolar100 MWactive2024-04MISO
4SIDNEY 1 - 4MIRA TAP 138.0kVSolar40 MWwithdrawn2022-03MISO

How Champaign County compares

#343 in the US · #14 in IL

Champaign County ranks #343 of 1,607 US counties by power waiting to connect, and #14 of 64 in Illinois.

CountyWaitingCapacity queued
Lee County126.4 GW
Will County54.3 GW
McLean County112.9 GW
Ogle County52.9 GW
LaSalle County72.8 GW
Christian County82.3 GW
Peoria County72.1 GW
Tazewell County101.9 GW

Common questions about power in Champaign County

How long does it take to get power for a data center in Champaign County, IL?

The median wait for a project still in the interconnection queue in Champaign County is 2.5 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 1 projects in Champaign County have reached energization and 7 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Champaign County, IL?

1.1 GW is currently requested across 7 active interconnection requests, and 150 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Champaign County, IL a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Illinois policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Champaign County — MISO — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.