Data centers and new power in Clinton County, IA

610 MW of new power is waiting to connect to the grid in Clinton County, IA — 3 active requests. Typical wait: 4.1 years. 3 projects are built, 1 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Clinton County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Clinton County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Clinton County right now.

610 MW
of new power is waiting to connect
3 projects asked. Not yet approved. Roughly what 488,000 homes use.
600 MW
has actually been built
3 projects switched on so far.
4.1 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 43%
  • Still waiting 43%
  • Withdrawn 14%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Clinton County.

What kind of power is asking to connect

  • Solar + battery 41%
  • Solar 33%
  • Natural gas 26%

By capacity requested. Data as of 14 October 2026.

All the numbers

7 requests ever filed
Pending applications
3
of 7 ever filed
Capacity queued
610 MW
requested, not committed
Already built
600 MW
3 projects connected
Built vs decided
75.0%
1 withdrawn
Median wait
4.1 yr
for applications still pending
Connected capacity
181 MW
indicator, see note

Source: interconnection queues published by MISO. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built3600 MW42.9%
Still waiting3610 MW42.9%
Withdrawn1125 MW14.3%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar + battery1250 MW
Solar1200 MW
Natural gas1160 MW

Key dates for projects here

1 dated · next closes 2027-09-10 (MISO)
QueueWhat closesClosesStanding
MISOMISO DPP-2026 Definitive Planning Phase application deadline
Attachment X of the tariff and BPM-015.
2027-09-10confirmed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 7 by size
ProjectTypeCapacityStatusFiledQueue
Salem - Rock Creek 345kV LineWind250 MWcompleted2019-04MISO
Calamus EastSolar + battery250 MWactive2021-07MISO
Calamus East 161 kV SubstationSolar200 MWcompleted2019-01MISO
Calamus EastSolar200 MWactive2025-07MISO
Beaver Channel 161 kV SubstationNatural gas160 MWactive2022-09MISO
Rock Creek 345 kV SubstationSolar150 MWcompleted2018-03MISO
Rock Creek-DeWitt 161kV lineSolar125 MWwithdrawn2020-06MISO

How Clinton County compares

#550 in the US · #5 in IA

Clinton County ranks #550 of 1,607 US counties by power waiting to connect, and #5 of 21 in Iowa.

CountyWaitingCapacity queued
Linn County102.3 GW
Cerro Gordo County51.4 GW
Washington County31.1 GW
Marshall County4717 MW
Franklin County3560 MW
Story County3550 MW
Webster County2470 MW
Muscatine County3329 MW

Common questions about power in Clinton County

How long does it take to get power for a data center in Clinton County, IA?

The median wait for a project still in the interconnection queue in Clinton County is 4.1 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 3 projects in Clinton County have reached energization and 1 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Clinton County, IA?

610 MW is currently requested across 3 active interconnection requests, and 600 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Clinton County, IA a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Iowa policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Clinton County — MISO — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.